Completion and Commissioning Manager offshore EPC Oil and Gas +wind turbine offshore

الخبرة

CAREER HISTORY

Control Contracting & Trading Company (CCTC) (from 9 May 2022)

Current Designation Completion &Commissioning Manager

Project 1: 11Kv Load migration from PGP to PDP UCC ADNOC offshore 60 MUSD

Project 2: Replacement of EDGS and LV system upgrade LOWER ZAKUM FIELD ADNOC offshore 50MUSD

Project 3: Scope of FOUR (4 nos.) site Schemes in IN UPPER ZAKUM FIELD ADNOC offshore 47 MUSD

Responsibility

  • Pre-com &Commissioning Execution Plan Development
  • Pre-commissioning and commissioning procedures
  • Integrated Project Schedule Development
  • Systemization of Plot Plans, PFDs, P&IDs & Specialty Equipment, Single Line Diagram, Cable Runs,

Safety Instrumented Systems, and instrumentation

  • Completion strategy
  • HSE plan and LOTO procedure
  • Systems & Subsystem breakdown
  • Vendor Coordination and vendor management and Surveillance and inspections for project equipment
  • Staffing plan/ Mobilization plan/OEM mobilization plan.
  • Follow up on Site Pre-commissioning and Commissioning activities for all disciplines.
  • Commissioning planning Level 4 and Level 5
  • Lead and attend weekly meetings/monthly meetings (progress, status, ..)
  • Attend FAT/SAT
  • Lead PSSR (Pre-Start-up Safety Review)

SSE Renewables (from August, 2021 to April, 2022)

Current Designation (E&I Commissioning Engineer)

Project 1: Seagreen offshore wind farm Topside.

Responsibility

Offshore Substation Platform (OSP) Topside Precommissioning,commissioning , Completions, and Handover ,

  • GIS 66KV Circuits 1,2 and 3 (ABB)
  • GIS 220KV Circuits 1,2 and 3 (ABB)
  • Transformers 220KV/66KV 390MVA (koncar) and auxiliary Transformers 66KV/0.415KV
  • Relay panels for GIS 66KV Circuits 1,2 and 3 ( ABB Relay REL650,REF 620,REB650,REB670)
  • Relay panels for GIS 220KV ( ABB Relay RED670,REC670,REF 620,RET615,RET670 and GE P40)
  • LV 415KV switchgear (ABB), SCADA (ABB), AC/DC UPS (Schneider), Fire & gas , inert gas, CAF and

HVAC.

  • Telecommunication.

Alasab General Transportation and Contracting LLC (November, 2020 to July, 2021)

Designation (E&I Construction and Commissioning Manager)

Project 1: ADNOC onshore/offshore EPC for Rumaitha Thamama Zone B Phase III Expansion Development

,Project Value: 175M$

Responsibility

Managing of Construction and Commissioning for new clusters and existing clusters.

  • OHL 33KV, ETR and ITR, Wellhead control panels and Chemical injection
  • Oil production, Gas lift, Water injection, Gas injection
  • Hot loop check, Tubing flushing, Pressure test, Hydro-test and Leak test

Petrofac International Ltd (October, 2018 to November, 2020)

Designation (E&I Principal Commissioning Engineer)

Project 1: TURKSTREAM, EPC, Client South stream, Turkey, Project Value: 400M$

Project 2: ADNOC onshore Qusahawira Field Development Phase II, EPC Abu Dhabi UAE, Project Value: 580M$

Responsibility

EI&T Lead Commissioning Engineer for GIS, MCC’S, LV Switchgear’s, 3 GEG (1 MW), OHL 33Kv, CDS,

WELLPADs, GLOPWH, WAGWH and GS2

  • Commissioning Execution Plan Development (also Discipline Plans)
  • Integrated Project Schedule Development
  • Systemization of Plot Plans, PFDs, P&IDs & Specialty Equipment, Single Line Diagram, Cable Runs,

Safety Instrumented Systems and instrumentation

  • Development of Turnover Folders, Systems Walk-down Packages, Pre-Commissioning, Commissioning

Procedures and Loop Folders

  • Implementation of LOTO P&IDs
  • Systemization of Systems & Sub system and MC Walk-downs
  • Vendor Coordination and vendor management and Surveillance and inspections for project equipment

JACOBS ENGINEERING (June, 2016 to September, 2018)

Designation (Deputy Commissioning Manager)

Project 1: Merah Khouribgha and Laayoune Mining EPCM, client OCP Morocco.

Responsibility

  • Ensure the safety, quality, value, timeliness of the project.
  • Develop, manage, and execute all commissioning and related activities in conformance with Jacobs engineering SA policies and procedures, contracts, plans, specifications, schedules and cost estimates.
  • Manage and supervise the commissioning of various systems including MV Electrical System, Generator engines, Mechanical and piping Systems, Integrated Automation Systems, Safety and Fire Systems.
  • Work closely with various stakeholders including OCP as client, The Project Manager, Engineering

Manager, Quality Manager and Construction team to provide subject-matter expert advice leadership.

Projects 2: Owner Project Investment (ODI) is one of the largest fertilizer EPCM projects in the world,

ODI1, ODI2, ODI3 and ODI4, Project Value: 2.5 billion usd

Responsibility

  • Improve the ODI Electrical systems break down, mark-up, operation test procedure…. Provide guidance to the Electrical discipline in accordance with contract agreement
  • Commissioning and startup Switchyard 60/10Kv 72MVA, Steam Turbine Generator 60MW, VFD, SST,

UPS, DC&AC batteries, MCC, MV Cells, ABB Relays and MV/LV Transforms 11Kv/0.42k, Start–up of units OSBL, SAP, PAP and DAP.

VINCI GROUP CEGELEC (September, 2011 to April, 2016)

Designation (Electrical Commissioning lead)

Projects : ODI 1, ODI 2, ODI 3 and ODI 4 Switchyard 60KV/10KV (Client JACOBS/OCP):

Responsibility

  • Follow up of quality inspections, Implementation of quality program.
  • Pre-commissioning of HV equipment’s (CT&VT, HT CB, Disconnectors & transforms 60/10 KV), MV panel ABB (Relays REF630, REF620, REF615, REB615, RED 615, REM620) and (LV PANEL, DC and

AC UPS AEG)

  • SCADA System of Switchyard 60KV/10KV (Relays F650, T60, MICOM P543, CC1000 and EPM600)
  • Commissioning and configuration of equipment (VFD et starters MV (Siemens), VFD LV (Siemens), MCC

(Siemens & Allen Bradley) Control and command of HV substations, MV PANEL ABB).

  • Commissioning with configuration of equipment’s, VFD (Schneider Electric), Protection Relays (Tesys)

and MCC (Okken)

  • Configuration and tests of energy metering system Iton SL7000 and power quality monitoring Alpes technology of Switchyard 225Kv of KHOURIBGA

Project : Renewable energy Wind Turbines farms onshore

  • WIND FARM HOUMA (50.6MW), 22 Siemens turbines with a unit capacity of 2.3 MW
  • WIND FARM FOUM EL OUED (50.6MW), 22 Siemens turbines with a unit capacity of 2.3 MW
  • WIND FARM AKHFENIR (101.87MW) 61 Alstom turbines with a unit power of 1.7 MW

Responsibility

Engineering

  • Preparation of design review , project specifications and philosophy for electrical equipment
  • I was also involve on Materiel procurement (preparations of material requisition ,vendor offer review ,

technical review and preparation purchase order )

  • Gate review and constructability review
  • Supporting Engineering team to develop GA drawing , Wiring circuit diagram , layout drawing for the

Switchyard 22KV/60KV

  • Reviewed and approved Cable size study for 22KV cable (WT) for Circuit 1,2,3 and 4
  • Coordination with vendors engineering department document review and approval (Schneider, Nexans, and

Siemens, AEG (UPS and batteries)).

  • Review Fire and gas drawing developed by vendor (GA drawing , loop diagram , layout drawing, termination drawing for JB and f&G Panel )
  • Supporting our engineering team for Lighting/Earthing /lightening for the switchgear 22kv/60KV Drawing
  • Reviewed and approved Cable routing and cable trouches was developed by our subcontractor

DELIVERABLES (OFFICE- ENGINEERING & PROCUREMENT STAGE)

  • System and Subsystem Breakdown (E&I-HVAC-Telecom)
  • Preparation of “Project Preservation Procedure”
  • Preparation of Method Statement
  • Preparation of “Operational Test Procedures” (OTP’s for energization)
  • Vendor Document Review (Factory Acceptance Test “FAT”/ Site Acceptance Test “SAT”, Asset Integrity

Management System “AIMS”) “Commissioning Spares Parts, Special Tools & 2 years Warranty Spares list”

Review & Approval

  • Attend Factory Acceptance Tests – issue FAT report- Track down Outstanding Punch (if any)
  • Population of Pre-com & Com activities within Completion Management Database
  • Establish Ready For Commissioning (RFC)/ Ready For Start Up (RFSU)/ Ready For Hand Over (RFHO)/

Provision Acceptance Certificate (PAC)/ Final Acceptance Certificate (FAC) Hand over procedure

  • Establish (by priorities) Commissioning & Start up Sequences & Vendor Mobilization Schedule
  • Preparation HSE Commissioning Plan (LOTO)

DELIVERABLES (SITE- CONSTRUCTION – PRE- COM & COMMISSIONING STAGE)

  • Follow up the Project Equipment Multidiscipline Preservation activities
  • Follow up cable pulling, termination, glanding , electrical equipment erection .
  • Ensure PTW ,coordinate work with other discipline
  • Supervise Cables Continuity & Insulation & Hi-Pot & Bus bar torqueing, Relay Protection Setting

Calibration, Loop testing …activities

  • Attend Mechanical Completion Walk-downs by Sub system
  • Follow up the Site Acceptance Testing & Mechanical Completion punch items close out & MC/RFC/ RFSU

Cert. Status

  • Issue Vendor Call out Instructions
  • Execute Operational Test Procedures (OTP`s)
  • Attend “Pre-com & Com & Hand over” Daily Progress Meeting
  • Lead Pre-Start up Safety Review “PSSR”
  • Assist & Supervise Performance Test

Project 11: « Renault Tangier RTM2 » (Client RENAULT)

Responsibility

  • Tests and commissioning of MV/LV PANEL (Schneider Electric)
  • Designed Layout drawing of cable tray, lighting and bus duct

SNEF GROUP MAPICER Morocco (August 2010 to August 2011)

Designation (Electrical Designer/ Commissioning)

Project: Renault automobile Manufactory Tanger

  • Electrical Designer of MV/LV PANEL.
  • Commissioning of switchyards MV/LV 22Kv/400Vac

VIELEC SA Casablanca Morocco (July 2009 to July /2010)

Designation (Electrical Designer)

Project 1 and 2: Dam TASKOURT and OUED ELMALEH AIC métallurgie

التعليم

EDUCATION

MBA-Business of Management

Girne American University UAE 2021/2022

Master’s Degree: Electrical Engineering.

Faculty of Sciences and Technologies, Hassan 1st

University, Settat, Morocco 2017/2018

Bachler’s Degree: Electrical Engineering

Faculty of Sciences and Technologies, Cadi Ayyad

University, Marrakesh, Morocco 2005/2009

التقييمات