Senior Chief Surveyor at SABBAGH ENGINEERING CONSULTANT (2011-12 – 2023-12)
- Oversee all survey operations including topographic surveys, setting out, and quantity verification across major municipal and civil projects.
- Review and study contract documents regarding cost, time, and contractual requirements to advise the Project Manager on potential variations, re-measurements, and claims.
- Prepare monthly quantity and payment certificates, ensuring full compliance with approved Requests for Information (RFIs) and local authority quality standards.
- Assist in generating daily, weekly, and monthly progress reports for executive management.
- Study & Design of Flood Control & Stormwater: Diriyah, Huraymila & Thadiq (Riyadh Area).
- Study & Design of Flood Control & Stormwater: Zulfi & Ghat Governorates (Contract No. 90).
- Construction Flood Control Measures: Wadi Qaws, Methwb & Ghulail Dams, Box Culverts, Sewer Lines, and Open Channel Lining in Jeddah City. (Client: Jeddah Development & Urban Regeneration Co. - JDURC)
Chief Surveyor (Arafat Area) at CRCC (CHINA RAILWAY CONSTRUCTION CORPORATION LIMITED) (2009-01 – 2011-11)
- Managed surveying activities for large-scale rail transit infrastructure.
- Key Project: Al Mashaear Al Moqadsah Metro.
- Client: Ministry of Municipal and Rural Affairs
- Consultant / Management: Dar Engineering, KA & SYSTRA
Chief Surveyor at MABANINA INTERNATIONAL EST. (2005-01 – 2009-01)
- Executed and supervised survey works for major infrastructure, sewage networks, and underground utility structures.
- Jeddah Gate Infrastructure & Underground Water Tanks (Sites 1 & 2). Client: Emaar Middle East | Consultant: Zuhair Fayez Partnership
- Main & Branch Sewer Lines & Lift Station (Contracts 16 & 18): North & Central Districts of Jeddah City. Client: General Directorate for Water | Consultant: Khatib & Alami
- Main & Branch Sewer Lines & Treatment Station (Contracts 20 & 27): South & Central Districts of Jeddah City. Client: General Directorate for Water | Consultant: Khatib & Alami
- Main Sewer Lines (Contracts 7 & 8): North & Central Districts of Jeddah. Client: General Directorate for Water | Consultant: ILF
Technical Office Surveyor at PEAKS COMPANY FOR CONTRACTING (2004-01 – 2005-01)
- Managed technical office survey data, quantity take-offs, and drawings.
- Key Project: Main Sewer Lines in North & Central Districts of Jeddah (Contracts 9 & 10).
- Client: General Directorate for Water | Consultant: ILF
Technical Office Surveyor at TUMPAIN CO. FOR CONTRACTING & MAINTENANCE (2002-02 – 2004-01)
- Provided survey controls, setting out support, and volume calculations for industrial developments.
- Key Projects: Development of Industrial City Phase 3, Phase 5, and Sewage Treatment Plant (S.T.P) in Jeddah.
- Client: Ministry of Industrial & Electricity | Consultant: Dr. Ahmad Abdul Wareth
Surveyor at EL EMAN COMPANY FOR ROAD CONSTRUCTION (EGYPT) (1999-10 – 2002-01)
- Conducted alignment surveys, cross-section leveling, and layout tasks for road and building construction.
- Key Projects: Single Road Construction in Egypt; Construction of 3 Schools in El Gharbia, Egypt.