Over twenty three (23) year of experience in the field of Engineering and Construction industry EPC (Oil & Gas, Petrochemical plant), Modification of platform Vessel and infrastructure.
الخبرة
Senior Quantity Surveyor (Engineering) - Saudi Arabian Bechtel Company (SABCO) - Bechtel Project, Jubail, K.S.A.
(2018-10 - 2020-07)
Royal Commission office - Engineering Dept. Bechtel Project, Jubail, RIC & Other Infrastructure.
- Reviewing Client design submittal, request for proposal (RFP), MTO, SOQP, design drawing and specification.
- Missing Pay item to be identified in 10%, 30%, 90% & 100% for review.
- Standardization of all Pay item & arrangements.
- All deliverables will presented to the QS Review form, including all MTO and RFP.
- Specification and drawing with proper comments on the submission.
- RC Standardization measurement rules will be guided in the preparation of reviewing the contract.
Senior Quantity Surveyor - Petrofac International Ltd - Sharjah and Dubai, United Arab Emirates; Gdansk, Poland
(2012-12 - 2016-05)
Petrofac Facilities Management Limited. Modification to Floating Production Vessel FPF1 Project Conversion – Gdansk - Poland (15 February 2016 to 12 May 2016 - 2nd assignment; November 2014 to 18 Feb 2015 - 1st assignment). Laggan Tormore Project: Fabrication Works for Module (27 nos.) located at Jebel Ali & Hamriya free zone.
- Identified Variation Order Material & labour rate if is based on subcontract unit rate.
- Searching all Variation Order submitted by client, which have a confirmation of duplication.
- Physically check, actual verification of completed work for Piping, Structural, Electrical & Instrumentation including Painting Works.
- Scaffolding measurement of actual installation & dismantling work that is part of additional scope of work for payment.
- Assessment of Variation Order and define base on the unit rate and contract agreement.
- Reviewing Method of measurement for the scope of work.
- Calculate total Quantity & price submitted if this are based on Bill of Quantity.
- Provide Back charges for Subcontractor that is using evidence as back up.
- Controls of Manpower & Equipment supply if they are based on Purchase order.
- Final settlement of contractor final account.
- Provide assistance in preparing the Scope of work.
- Coordinate with construction team for overall performance.
- Oversee the tendering of project works for main contractors by evaluating payment application, cost control, evaluation of subcontractors, client invoicing and issuing payment certificates.
- Valuation and invoicing for works in progress.
- Cost control and reporting for work in progress.
Senior Quantity Surveyor - Petrofac International Ltd - Algeria
(2011-12 - 2012-10)
In Salah Gas (ISG), Southern field development project (SFDP), Algeria Sonatra, B.Petroleum. Contract Price Approx. US$ 2.4 Billion.
- Preparation of Bill of Quantity (BOQ), Structural Steel, Piping, and Mechanical & Electrical Instrumentation works.
- Total Quantity is based on Method on Measurement incorporate in related on scope of work with unit rate to perform the basis of payment.
- Analysing all unit rates with some additional are not included during the bidding time.
- Reviewing Subcontractor submitted Quantity has & evaluated base on contract unit rate as indicated. Payment Certificate will prepare for invoicing purposes.
- Work in Variation Order if the works are part of Original Scope of Work.
- Closed out all Bill of Quantity's, having checked and recognize drawing as indicated as (IFC) Issued for Construction.
- Total Value of Bill of Quantity as comparing the Value of Original Amount it is ahead for the purpose of Project Budget Amount.
- Preparation of material take-off @ quantity take-off from drawings.
- Preparation of unit rate analysis of piping @ mechanical works.
- Assisting to subcontract engineer all method of work to fill up quantity & rate for submission to management for review.
- Assisting BID Quantity proposal set up, by subcontractor and arrangement of offer price amount.
- Base on price proposal and preparation for BID Tabulation for subcontract price.
- Monitoring subcontractor quantity proposal that is line with BID procedure.
- Identified item rate that are not included on the submission for the record.
- Man-hours distribution equivalent to work.
- BID Quantity proposal set up, subcontractor offer arrangement of submitted price rate.
Senior Quantity Surveyor (Sub Contracts) - Petrofac International Ltd - Kazakhstan
(2006-06 - 2011-08)
Kashagan Development Experimental Program, AGIP KAZAKHSTAN NORTH CASPIAN OPERATING COMPANY, Republic of Kazakhstan. Petrofac-Agip KCO. Contract Price Approx. US$ 844,455,000.
- All Subcontract and QS documents shall provide in accordance with Subcontract administration policy procedures shall have requirement on the project.
- Preparation of Subcontract Bill of Quantity (BOQ) includes such discipline as per category.
- Analysed required progress work breakdown percentage, giving proper control of work payment.
- Stipulated subcontract progress procedure, does in line with method of measurement.
- Allocated unit rate, for subcontractor invoices, verifying monthly progress & reviewing quantity based on actual site situation.
- Coordinating to Subcontractor the allocated format of back up report.
- Ensuring all Subcontractor quantity has reported is being evaluated as per subcontract responsibilities.
- Identified variation proposal on the project, determine each item of work activities.
- Issuing Subcontract payment certificate, which control the status of payment.
- All Quantities have preparation for final Measurement as on AS BUILT drawing.
Cost Control Engineer - Qatar Engineering Construction (formerly Q Ship) - Mesaieed, State of Qatar, Doha
(2004-03 - 2006-06)
PSIK-II OXY Jacket Fabrication & Installation, Client – S.M.O.E. of Singapore. Anchor Handling Tug Vessel (2) & Fcb Cement, Client – Halul Offshore & fcb ciment.
- Prepare progress Valuation on the contract agreement of price schedule.
- Evaluate unit rate of the bill of quantities to the actual quantities executed.
- Controls all Job Order & work order for monthly billing work.
- Review contract agreement to implement variation order.