APTIM Services Sherwood Park, AB December 2022-Present
Fabrication Superintendent
- Supervising and coordinating activities of pipe fitters and welders to ensure efficient fabrication and welding processes.
- Managing and training crews on safety practices to maintain a safe working environment for workers.
- Working collaboratively with project managers, engineering teams, and other stakeholders to provide cost-effective project solutions.
- Preparing and overseeing the fabrication schedule to ensure timely delivery of materials and completion of projects.
- Providing regular reports to upper management on the status of fabrication projects, timelines,
and budgetary requirements.
Suncor Energy Fort McMurray, AB August 2021-Present
Turnaround Planner/ Coordinator
- Mechanical and Piping Planner for 2023 - 5 year annual
- Maintenance Coordinator
APTIM Services Fort McMurray, AB August 2019-2021
Piping Superintendent
- Planning and optimization Suncor 2020/2021
- Planning/ Execution Suncor 2020 Spring Turnaround Base Plant
- Planning/ Execution Suncor 2019 High Pressure Steam Mitigation Project
- Planning/ Execution Suncor 2019 Fall Turnaround Base Plant
Melloy Industrial Services Redwater, AB July 2019-August 2019
Foreman/ Maintenance Supervisor
- Agrium Fertilizer Plant; supervised the daily activities of 10 Pipefitters and Welders
APTIM Services Sarnia, ON Feb 2017-June-2019
Piping Superintendent
- Suncor Spring Turnaround; managed day to day activities of 100 Pipefitters and Welders
- Direct projects progress to ensure that activities implemented a timely manner
- Plan/schedule maintenance work, monitor performance and identify improvement opportunities
Melloy Industrial Services Redwater, AB Aug 2017-Feb 2018
Foreman/ Maintenance Supervisor (Contractor)
- Agrium Fertilizer Plant; supervised the daily activities of 20 Pipefitters and Welders
AECON Group Inc. Various Locations, AB Nov 2015-Aug 2017
Senior General Foreman/General Foreman/ Construction Coordinator
- Supervise crews of 60 steamfitters and welders on the CDH 3 Project for Pembina
- Planned and executed Flare line and Stack at Northwest Upgrader
- Development and maintenance of 2-week look-ahead plans and schedules
Horton CBI Limited Fort Saskatchewan, AB Jan 2015-Nov 2016
Construction Coordinator
- Initiated RFI's to ensure isometrics are built to design
- Manage custody transfer between trades
- Liaised with fabricator and mod yard, proofed mark ups and assisted fabricator with issues
- Monitored gauges, torque wrenches, PSV's, welding machines to ensure certs are up to date
- Schedule final walkdowns with client and execute
Piping Supervisor
- Analyze and interpret isometric drawings and general arrangements
- Maintain and execute the project plan; ensured ongoing quality control initiatives
- In charge of all heavy lifts on site
- Coordinated cranes to ensure correct load capacities were met
Horton CBI Limited Fort Saskatchewan, Alberta Oct 2012-Jan
2014
Quality Inspections/Hydrotest Coordinator (Sept 2013-Jan 2014)
General Foreman (Jan 2013-Sept 2013)
Punchlist Foreman (Oct 2012-Dec 2012)
- Supervised the preparation of test activities; examined systems for completeness/readiness
- Monitored hydrotesting (hydrostatic & pneumatic), handled reports, supervised line cleaning
- Ensured the project progresses accordingly and identified issues or deviations
- Participated in client inspections and on-site safety walks and completed hazards analysis
- Worked with tradespeople to get ideas on process improvement and identify safety concerns