im interested to working of the GE
Company: Industrial assembly company / ETTERKIB / Sonalgaz group subsidiary.
Grade:Electrical Installation Team Leader. December 2008 to February 2010.
Location: Power plant gas Turbine Larbaa (4 x 139.9 Mw) and AIS substation (60 / 22OKV).
-Role and responsibilities (Electrical assembly of the AIS substation):
- Role and responsibilities (Electrical installation of the power Plant ):
-Installation, installation and connection of AIRO lighting fixtures and
Main transformer, filling and auxiliaries.
-Installation of disconnector, T.T and TC, surge arrester of the station of each turbine.
-Mounting of supports and installation of batteries for each turbine.
II- Studies:
A- Secondary education:
Degree: BAC Electro technique.Year: 92/93.
Location: Cherchell Technical College.
B- University studies:
Degree: Diploma of Applied University Studies in Electrotechniques.