JP Dunn Construction
Construction Manager
April 2022 – Present
St Peter’s College accommodation (£11 Million project)- the ultra-low carbon Passive House project, constructing 54 bedrooms across two buildings.
- Took ownership of planning, monitored progress and I brought solutions to the technical aspects, removed blockers that were present.
- I employed a good team of workers in this critical time, and I made it possible for the work to progress according to the look ahead plan.
- Prepared Permits, established costs, discussed blueprints and plans with contractors and consulted with Engineers.
- Actively involved in improvement of processes and optimization of activities.
Volker Laser
Senior Site Manager
May 2020 – April 2022
Battersea Power Station Ph. 3A (£8 Billion project) a project consisting of 3 buildings.
- Produced and developed project programmes and controlled operations to deliver of the project on time.
- Controlled additional costs for non-productive costs and expenditure. Reviewed progress and liaising with the Quantity Surveyors to monitor costs.
- Developed clear and achievable objectives relating to budget, manpower, materials and scheduling.
- Responsible for health and safety and quality inspections (Alumasc and BCO inspector) and HO of completed works.
EWR Alliance
Site Manager
August 2019 – March 2020
Environmental Mitigation Civils Site B14 & B28 / BFO Site
- Bat House Construction, Site Fencing, Earthworks to New Ponds, Installation of Life Buoys, Reptile Embankments, Gravel/Rubble Area, Hibernaculum Installation, Log Piles, Compost Piles, Badger Sett
- Parapet Removal, Bearing Inspection, Possession work, Temporary work
- Followed works programme, achieving all the critical milestones.
- Providing accurate and regular reports on progress and dates
- Demonstrated ability to motivate the team, towards achieving higher standards of health and safety and product quality.
Salix Site
General Foreman
September 2018 – July 2019
Woodhall Park Estate, Watton at Stone
- Took responsibility for all Groundworkers, Steel Fixers, Shuttering Carpenter, Concrete Finisher, Strikers and Labourers for the construction of a new river channel building the retaining wall with capping beams and a new weir.
Henry Construction
General Foreman
March 2018 – August 2018
Milton Road, Cambridge
- Oversaw the erecting of a concrete frame building for an aparthotel.
- Completed site inspections as required while ensuring tasks were completed to client specification.
Modebest
Foreman
Dec 2017 – Feb 2018
Brooklands Square Site in Milton Keynes
- Supervised activities on the building of apartment blocks with commercial space on the ground floor.
JB Development
General Foreman
Sep 2017 – Nov 2017
The Exchange Site in Aylesbury (£110 Million project)
- Employed to assist with delivery of valuable assets for the project that included the building of 4 restaurants and 47 apartments.
M.J. Gallagher
Foreman
May 2017 – Aug 2017
University Site in Cambridge
- Managed day to day site operations and ensured that construction projects were completed in time and within budget.
Byrne Bros Ltd
Foreman
Aug 2016 – Apr 2017
Cambridge /Astra Zeneka Laboratory (£1 Billion project)
- Formed part of the team tasked to create the ultra-modern health and research centre.
CSJV
Section Foreman
Jan 2016 -Aug 2016
Crossrail Paddington C405 £150 Million project as part of the £14.8 Billon Crossrail programme.
- Made responsible for Temporary Works as well as King Post Wall Shuttering, Erecting Track Slab Infill, Hoarding Fence, installation of Platform Hoarding and the relocation of the Bus Driver’s Toilet to Chilworth Street Compound
- Prepared updates on progress and cooperated closely with commercial department.
- Effectively enforced quality control and health and safety compliance.
Kendrick Ltd
Site Manager
Sep 2015 – Jan 2016
Commissioned to oversee the building of schools for Interserve Construction in Watford and Kings Langley
Carpenter / Supervisor / Foreman; 2003 – 2015
Provided services to multiple large contractors, accomplishing assorted types of projects.