Assistant General Manager - Hydrotest & Commissioning - Advance Infrastructure Private Limited - Purnia, Bihar
(2026-01)
Project: Paradip Numaligarh Crude Pipeline Project (199 km, 26" OD Crude Pipeline). Client: M/s GAIL (India) Limited. Project Management Consultant (PMC): Engineer India Limited.
Resident Construction Manager (RCM) - Client-Approved Spread In charge - Jaihind Projects Limited (on behalf of M/s Shree Omkar Enterprises) - Nagpur, Maharashtra
(2022-11 - 2026-01)
Project: Nagpur–Chhindwara–Jabalpur Pipeline Project. Client: M/s GAIL (India) Limited. Project Management Consultant (PMC): Worley Services India Private Limited (WSIPL).
- Handled overall site execution for large-diameter cross-country gas pipeline projects, ensuring adherence to project timelines, technical specifications, and quality standards.
- Coordinated with Client, Project Management Consultant (PMC) & Third-Party Inspection (TPI), and internal teams to ensure smooth communication and timely decision-making.
- Supervised critical activities including Stringing, Welding, Coating, Trenching, Lowering, Backfilling, Hydro testing, Swabbing, Drying, and Pre-Commissioning & Commissioning.
- Managed subcontractors, manpower planning, and resource allocation to achieve daily, weekly, and monthly targets.
- Ensured strict compliance with HSE protocols, regulatory guidelines, and company policies throughout project execution.
- Oversaw preparation and review of daily progress reports, pipe book, hydro test plans, test packs, reports, and mechanical completion documentation.
- Led punch list resolution, final inspections, and handover activities in coordination with the Client and PMC.
- Identified potential risks and implemented timely corrective measures to avoid project delays or non-compliance.
- Ensuring compliance with project specifications, HSE protocols, and regulatory requirements.
Manager – Hydrotest & Commissioning - Kalpataru Power Transmission Limited - Jhunjhunu, Rajasthan
(2019-08 - 2022-10)
Project: Mehsana–Bathinda Pipeline Project (134 km, 30" OD Gas Pipeline). Client: GSPL India Gasnet Ltd. (GIGL). PMC: VCS Quality Services Pvt. Ltd.
- Handled overall site execution for large-diameter cross-country gas pipeline projects, ensuring adherence to project timelines, technical specifications, and quality standards.
- Coordinated with Client, Project Management Consultant (PMC) & Third-Party Inspection (TPI), and internal teams to ensure smooth communication and timely decision-making.
- Supervised critical activities including Stringing, Welding, Coating, Trenching, Lowering, Backfilling, Hydro testing, Swabbing, Drying, and Pre-Commissioning & Commissioning.
- Managed subcontractors, manpower planning, and resource allocation to achieve daily, weekly, and monthly targets.
- Ensured strict compliance with HSE protocols, regulatory guidelines, and company policies throughout project execution.
- Oversaw preparation and review of daily progress reports, pipebook, hydro test plans, test packs, reports, and mechanical completion documentation.
- Led punch list resolution, final inspections, and handover activities in coordination with the Client and PMC.
- Identified potential risks and implemented timely corrective measures to avoid project delays or non-compliance.
- Ensuring compliance with project specifications, HSE protocols, and regulatory requirements.
Manager – Execution - Kalpataru Power Transmission Limited - Bhupalpally - Talegana
(2019-06 - 2022-10)
Project: Mallavaram–Bhopal–Bhilwara–Vijaipur Pipeline Project (350 km × 18" Pipeline). Client: GSPL India Gasnet Limited. (GITL). PMC: VCS Quality Services Pvt. Ltd.
- Executed Hydro testing, Pre-Commissioning, and commissioning activities for the 18" cross-country natural gas pipeline.
- Planned and coordinated hydro test operations and related activities as per project schedule.
- Coordinated with Client, PMC, and TPIA for inspections, approvals, hydro test operations including filling, pressurization, pressure holding, dewatering, and documentation.
- Monitored progress and ensured timely completion of assigned activities.
- Maintained hydro test records and progress reports.
- Ensured compliance with quality, safety, and HSE requirements at site.
- Supervised pre-commissioning activities such as cleaning, gauging, swabbing, and drying of pipeline sections.
Manager – Hydrotest & Commissioning - EPC Constructions India Ltd. (formerly Essar Projects India Ltd.) - Amritsar, Punjab
(2017-07 - 2018-10)
Project: Jalandhar–Amritsar Pipeline Project (100 km – 12", 16", and 18" OD Pipelines). Client: GSPL India Gasnet Ltd. (GIGL). Consultant: Sanmarg Projects Pvt. Ltd. (SPPL). TPIA: Certification Engineers International Ltd. (CEIL).
- Supervised hydro testing and commissioning operations across multiple pipeline diameters.
- Coordinated cleaning, gauging, hydro testing, dewatering, swabbing, drying, and leak testing.
- Reviewed work procedures, test reports, and ensured alignment with client and consultant requirements.
- Collaborated with QA/QC, HSE, and third-party inspection agencies to meet all compliance standards.
- Prepared final test documentation and supported successful mechanical completion and handover.
Manager – Hydrotest & Commissioning - Essar Projects India Limited - Vadodara, Gujarat
(2016-09 - 2017-07)
Project: Koyali–Viramgam Replacement Pipeline Project (157 km, 18" OD Crude Oil Pipeline). Client & PMC: Indian Oil Corporation Ltd. (IOCL).
- Directed hydro testing and pre-commissioning operations along the 157 km pipeline route.
- Oversaw cleaning, gauging, hydro test execution, dewatering, swabbing, drying, and pressure verification.
- Ensured strict compliance with IOCL's engineering standards and safety protocols.
- Coordinated with IOCL teams for inspection, test pack approvals, and punch point closures.
- Maintained detailed reports, project logs, and supported successful mechanical completion.
Deputy Manager – Hydrotest & Commissioning - IL&FS Engineering & Construction Company Limited - Surathkal, Karnataka
(2015-05 - 2015-09)
Project: Mangalore–Padur Pipeline Project (45 km – 48" & 42" OD Crude Oil Pipelines). Client: Indian Strategic Petroleum Reserves Ltd. (ISPRL). PMC: Engineers India Ltd. (EIL).
- Managed hydro testing operations for large-diameter crude oil pipelines (48" & 42").
- Executed all related activities including cleaning, gauging, hydro testing, and dewatering.
- Assisted in the preparation of hydro test procedures, test packs, and reporting formats.
- Coordinated with client (ISPRL) and PMC (EIL) for witnessing tests and resolving technical issues.
- Ensured high standards of safety and quality during pressure testing and pipeline integrity validation.
Deputy Manager – Hydrotest & Commissioning - Kalpataru Power Transmission Limited - Navi Mumbai, Maharashtra
(2014-06 - 2015-04)
Project: Uran–Chakan–Shikrapur Pipeline Project (160 km – 10" & 12" OD LPG Pipeline). Client: Hindustan Petroleum Corporation Ltd. (HPCL). PMC: Mott MacDonald Pvt. Ltd.
- Oversaw hydro testing operations for 10" and 12" diameter LPG pipelines across a 160 km stretch.
- Directed activities including cleaning, gauging, and hydro testing, dewatering, and drying.
- Reviewed and implemented hydro test plans and safety procedures in compliance with HPCL standards.
- Coordinated with PMC and client teams for inspections, approvals, and documentation.
- Ensured timely completion of work while maintaining safety, environmental standards.