RESPONSIBILITIES AS PROJECT ENGINEER AND FIELD ENGINEER IN TRANS ASIA AND IN NARMADA
OFFSHORE CONST PVT LTD.
- Competent of Pre-commissioning activity like Cleaning , Gauging ,Water filling, Hydrotesting, Dewatering,
Swabbing, EGP (Electronic Caliper survey), Air Drying/Vacuum Drying ,Nitrogen Purging.
- Responsibilities include Engineering and Technical & Project Management for Pipeline Pre-Commissioning
Services.
Procedure
Preparation & approval, Liaison with Contractor, Project Management, Resources
Management.
- Acquired exposure in pipeline pigging for gauging, base line survey, and tool running and caliper pigging
Activities.
- Conducted and inspected pipeline hydro test activities such as pre-testing of headers, water filling of Pipeline,
pressurizing, pressure calculations, dewatering, swabbing, nitrogen purging, etc.
- Handled decommissioning and pipeline pre-commissioning activities, oil pipelines, managed tie in of new pipelines etc.,
- Administered fabrication & erection of Structural Jobs and maintained its quality control procedures.
- Identified job hazard, undertook risk analysis, implemented, and inspected all safety precautions at the worksite.
- Co-coordinating and assisting the offshore projects, materials preparation, equipment’s function, engineering,
and implementation of the projects.
- Back support and preparation work for the project as per procedure, knowledge, experience, field studies and technical services.
- Trained for safety monitoring during fabrication, oil and gas commissioning activities and Hydro testing etc.,
- Documentation of history sheet, test pack clearing, etc.
TEXOL ENGINEERING PVT LTD.
- Prepare the checklist for the customer's site readiness and arrange the customer's consent on site readiness through effective follow-up.
- Simultaneously, get the project handover documents from the project department, scrutinize the documents for accuracy and completeness, assist the coordinator (C&Q) to prepare the cost estimate for the visit to the customers' site (with the day-wise plan, site schedule, boarding-lodging, local conveyance, etc.), and arrange to get approval from the top managment.
- Before FAT (Factory acceptance test) complete P&ID walk trhugh has been done and list out the punch points and try to closing of the punch points before site mobilization.
- Work/Service Order of Third Party Contractor (TPC) at the Customer's Site (after selecting a Validated TPC,
receiving, comparing, and finalizing the quote from the TPC) and the Issuance-and-Receipt of the Work/Service
Order by the TPC.
- Upon reaching the Customer's Site, Arrange to Unload the Consignment (if in the scope) at/near the Customer's
Facility.
- Ensure the Gate Entry procedures, as per the Customer's pre-determined Material Entry procedures and the safe-
&-secure positioning of the Consignment at the pre-determined location of the Customer.
- Arrange to Unpack the Consignment, Reconcile the material as per the pre-pared Packing List and Shift-&-Position-
&-Install the respective Systems/Equipment's at the precise location as per the pre-Approved relevant Drawings.
- Site Piping Fabrication-&-Installation, as per pre-Approved Piping &Instrumentation Drawings (P&ID).
- Insulation, as per Good Engineering Practices, Cable Tray, Conduit, Tubing and Cabling as per pre-Approved
General Arrangement (GA) & Room Layout Drawings.
- In the event the Assignment is that of Modification / Upgradation of a System supplied in the past, The Customer's requirements should be internally discussed, finalized, documented, compared with the past Documents, got analyzed-&-validated with the concerned internal Depts. for feasibility, got approved by the Customer for Scope-&-
Cost resulting in a Purchase Order from the Customer.
- Adherence to the pre-Approved Completion Timelines.
- Conformation to mandatory Regulatory requirements in terms of Statutory Certification and Quality Standards.
- Maintenance of all relevant Site-related Records of Attendance, Update of Man-days, Daily/Weekly SAT updates,
Deviation-&-Resolution updates.
- The Site-Bill of the TPC/s are discussed-&-finalized and that there are no doubts / disputes. All the necessary Site
Expenditures should result in Invoices that are unambiguous, reasonably justifiable and optimally quantified.
- Regular Verbal-&-Written Communication with Head Office / HOD .