Project Engineer - INDITRON ENTERPRISES PVT. LTD. - Gat No. 406 P, Mulshi, Pune
(2024-12-19 - 2026-03-19)
Proposed Industrial building project execution and management
- Acted as Project In charge on site, In-dependently coordinating with Architects, Structural Consultants, PMC and Civil + MEP Vendors to ensure smooth execution as per design intent.
- Successfully handled local stakeholder issues, including negotiations and conflict resolution with villagers, to maintain project continuity and social harmony.
- Executed and monitored industrial building from start to end works including RCC, PEB, EOT crane, Passenger and goods lift, glass façade, Internal roads, MEP works and finishing works etc.
- Maintained high quality standards and compliance with safety regulations.
- Execution of civil construction at site, including supervision of the work done by the contractor, preparing construction schedule and timely monitoring of the progress.
- Managed Site readiness for stressing operations, including curing status, cube strength verification, and approval protocols.
- Facilitated MEP coordination, ensuring clash free installation with structural and architectural elements.
- Reviewed the progress achieved, the program situation and highlighted the significant problems.
- Assisted in material procurement planning and ensured timely delivery of critical items by coordinating with purchase and logistics teams.
- Preparing DPR and MIS of the Projects and presenting it to the Directors on weekly basis.
- Prepared and maintained records of inspection reports, test results, and material approvals for client reference.
- Conducted quality checks on materials and workmanship, ensuring compliance with industry standards and client requirement.
Project Coordinator (Civil + Mep) - K.V. STAFFING SERVICES - Firodia Institute of Philosophy, Culture and History, Force Motors
(2022-01-27 - 2024-10-14)
Large-scale museum project execution and coordination
- Project execution activities for a large-scale museum project (around 450 Cr) ensuring alignment between site teams, contractors, PMC.
- Monitoring the progress of project work, Civil, Mep, Interior & Exterior fit-outs.
- Coordination with architect, consultants, PMC & vendors.
- Coordinated along GM with Post-Tensioning (PT) vendor for design approvals, layout finalization, and site execution of PT slab and beams.
- Preparation of budgetary cost, estimation bill of materials as per drawings and rate analysis for all Items In BOQ, costing and finalization of rates with vendors.
- Actively involved in preparation and co-ordination of LEED documents and sustainability compliance records.
- Reviewed the progress achieved, the program situation and highlighted the significant problems.
- Clearance given to respective vendor for further construction phase as per Panchasil checklist or Client requirement.
- Preparing DPR and monthly detail report and sent to General manager and directors.
- To co-ordinate with the PMC quality engineers, contractor representative for inspection and meeting about quality work related problems including closer of NCR.
- Coordinated works: RCC, Waterproofing, PHE, Firefighting, Fabrication, Internal roads, Lifts, Dry wall, flooring, Stone cladding, Glass façade and fins, furniture, painting.
Civil Site Engineer - DHANESH GANDHI
(2019-09-07 - 2022-01-26)
PMC, PWD GOVERNMENT CONTRACTOR
- Execution of civil construction onsite.
- Prepare measurement sheets from onsite data & drawings.
- Estimation of building construction material, BBS.
- Co-ordination of residential/Industrial construction site.
- Co-ordinate with client and contractor to Sub-Contractorsfor smooth flow of work.
- Supervision on finishing work activities.
- Reviewed the working drawing of contractor.
- Check quality of raw material & concrete.
- Coordinator of various civil work as per tender abstract/estimate.
- Documentation: a) Client cube test reports b) Material testing reports c) Trial sheet reports d) Monthly reports e) Preparing measurement bill sheets as per tender abstract/estimate.