Site Engineer - SK Construction PVT - Peundurai
(2026-06 - 2026-07)
Executed works based on Civil drawings. Purchase executive in construction handles all material purchasing and coordination for the project site.
- Prepared & verified the bills for payment
- Maintained DLR, DPR & Records as per ISO standards
- Arranged and mobilized contractors for executing the works without interrupting the schedule
- Coordinated with the project manager for planning & preparing the schedule for assessing the critical paths
- Prepared Bar Bending Schedule
- Prepared B.O.Qs for Concrete and Shuttering
- Conducted Safety Tools Box meeting for laborers at site
- Coordinated with other professional consultant representatives (Architects, Interior Decorators, Electrical and structural Engineers) when required and implemented as per their suggestions after approval
- Site setting out as per layout, ensured column Centre lines, alignment of beams & foundation work
- Snagging inspection after completion of the work
- Inspected, monitored and assessed Health and safety Hazards on site
- Arranged and displayed safety signs at appropriate locations and carried out safety measures on site
- Purchase construction materials: Cement, steel, sand, Aggregates, bricks, Electrical & plumbing items
Site Engineer - DEEJOS PVT LTD - Coimbatore
(2026-03 - 2026-05)
Executed works based on Civil drawings. Purchase executive in construction handles all material purchasing and coordination for the project site.
- Prepared & verified the bills for payment
- Maintained DLR, DPR & Records as per ISO standards
- Arranged and mobilized contractors for executing the works without interrupting the schedule
- Coordinated with the project manager for planning & preparing the schedule for assessing the critical paths
- Prepared Bar Bending Schedule
- Prepared B.O.Qs for Concrete and Shuttering
- Conducted Safety Tools Box meeting for laborers at site
- Coordinated with other professional consultant representatives (Architects, Interior Decorators, Electrical and structural Engineers) when required and implemented as per their suggestions after approval
- Site setting out as per layout, ensured column Centre lines, alignment of beams & foundation works
- Snagging inspection after completion of the work
- Inspected, monitored and assessed Health and safety Hazards on site
- Arranged and displayed safety signs at appropriate locations and carried out safety measures on site
- Purchase construction materials: Cement, steel, sand, Aggregates, bricks, Electrical & plumbing items
Site Engineer - RGP construction
(2025-04 - 2026-02)
Executed works based on Civil drawings for government building project.
- Prepared & verified the bills for payment
- Maintained DLR, DPR & Records as per ISO standards
- Arranged and mobilized contractors for executing the works without interrupting the schedule
- Coordinated with the project manager for planning & preparing the schedule for assessing the critical paths
- Prepared Bar Bending Schedule
- Prepared B.O.Qs for Concrete and Shuttering
- Conducted Safety Tools Box meeting for laborers at site
- Coordinated with other professional consultant representatives (Architects, Interior Decorators, Electrical and structural Engineers) when required and implemented as per their suggestions after approval
- Site setting out as per layout, ensured column Centre lines, alignment of beams & foundation works
- Conducted snagging inspection after completion of the works
- Inspected, monitored and assessed Health and safety Hazards on site
- Arranged and displayed safety signs at appropriate locations and carried out safety measures on site
Quality Control - PrayogProjects
(2022-09 - 2025-03)
Four Laning of Gobi - Erode Section of SH-15 from Km 123+000 to Km153+600. Built up area–30.600Km; Project cost–272.53Crores.
- Prepared Daily Work Progress and Daily Activity Report for Roadwork, Drain, Culvert
- Prepared Weekly program & progress status for TNRSP II Department, Work plan for month wise details for Utility (EB & TWAD) status
- Prepared Covering letter for Documents & Drawings to TNRSP-II office
- Used ERP tool of BSF (Built Super-Fast) for daily Labour work and machinery work details
- Prepared Program of work to TNRSP-II format
- Coordinated test report with QC for consolidate format
- Preparing strip chart and flow chart for site meetings
- Preparing Bill of Quantity of IPC Billed and unbilled work details
- Created the work schedule for Urban, Rural & Realignment areas in LHS & RHS sides
- Obtaining documents for Daily Progress Reports & Monthly Maintenance Program Reports
- Prepared work progress schedule: evaluated Action plan, financial program and chainage wise program
- Tree cutting progress, Drawing approval – Plan & Profile Road & Drain
- Retaining wall drawing, miscellaneous drawing
- Material approval – Cement, Steel, Sub base soil test, GSB design mix, WMM design mix
- Paver block work Earthwork and laying at site
- Minor bridge at site 3 bridges work
- QC building government office work at site
- Thermoplastic line at site
- Roundabout work at site
- Arch plastering work at site
- Pedestrian guard rail work at site
- Culvert And drainage work at site
- Street lights laying work at site
- Stud and Anti glare work at site
- Drain cover slab work at site
- FDD test subgrade, gsb, wmm first, wmm top layer at site
- Cube test at camp office
- Slump test at site
Temporary Site Engineer - PWD - Bhavani
(2021-08 - 2022-02)
Supervised daily construction activities for the Anicut (check dam) project in Erode, ensuring adherence to PWD manuals and safety standards.
- Monitored material quality (e.g, concrete, steel) and site progress collaborating with senior engineers to maintain project timelines
Site Engineer - Aavin - Cithode
(2020-01 - 2022-02)
Worked as site Engineer monitoring daily site activities and civil works projects within Aavin facilities (e.g: dairy plants, office buildings).
- Developed handbooks and documents related to project design and execution
Site Engineer - Selliamman Construction
(2018-03 - 2020-03)
Worked on highway road project Kangayam-Karur NH44.
- Led projects to successful completion, enhancing client satisfaction
- Coordinated teams, boosting productivity and collaboration
- Ensured compliance with safety standards, minimizing risks
- Conducted site inspections, maintaining high quality standards
- Developed strong client relationships, driving repeat business