Assistant Engineer - Aarvee Engineering Consultants Limited. In Association with Aim consultant - Sehore distt (M.P)
(2024-10)
To review and monitor/supervise the ongoing work on site as per approved designs, drawings, specifications in line with approved QAQC plan. To report and interacting with Team Leader for day-to-day work. Coordinate with client and the contractors appointed by client for execution of work water supply schemes to monitor construction work as per the schedule of each works.
- To check 100% of measurement & will witness 25% of field test quality of all works
- To review Quality Assurance Quality Control (QAQC) system of the SQC team and monitor if the ongoing work on site as per approved designs, drawings, specifications in line with approved QAQC plan
- Monitor progress with reference to pre-fixed targets drawn up jointly with the Contractors and furnish monthly progress reports in the formats as decided in consultation with the MPJNM
- To direct contractor to take all necessary steps to maintain the rate of progress of works as per the approval programmed
- Guiding team of Field Quality Control Engineers to approve setting out of the works layout, to verify the drawings of the contractor, quality control & Quality assurance procedures, etc.
- Ensure monitoring and checking of day to day works ongoing on the site, and issue monthly/interim payment certificates
- To direct the Contractor in all matters concerning construction safety
- To verify and correct the as built drawings
- Record measurements in measurement books at various stages of works, verification of measurement and preparation of bills based on recorded measurements jointly with the Departmental Officers during each stage
- Quality maintains according to drawing and specification
- Supervision of RWPM 1200 MM dia MS pipe work
- Supervision of CWPM 700,750,800 & 900 MM dia MS pipe work
- Supervision of 63 mm to 200 mm dia. HDPE pipe & 150 to 350 mm dia. DI K-7 distribution system pipe laying work
- Supervision of MBR & IPS
- Supervision 150mm to 600 mm, Dia. K-9 Clear Water Gravity Main Pipe Laying work
- Supervision of Raw Water Rising Main 500 Dia. DI K-9 Pipe Laying work
- Testing of material, Cube Test, Impact Value Test, Sieve Test, Water Absorption Test, Slump Test done at lab at field time to time
- Supervision of BT Road Restoration and CC road restoration work
- Supervision of OHTs of 75KL to 490 kl work
- Strictly monitor the progress of work for timely completion of the project
- Prepared contactor's bill
- Supervision of Sluice valve, Air valve & Scour valve, NRV, Butterfly Valve, chamber, construction work
- Supervision & Construction of WTP 111 MLD & Intake well 128.76 MLD
- Co-ordination with, Contractors & Clients
Field Engineer-CIVIL - Tata Consulting Engineers Ltd. - Sarni betul distt Bhopal (M.P)
(2021-04 - 2024-10)
To review and monitor/supervise the ongoing work on site as per approved designs, drawings, specifications in line with approved QAQC plan. To report and interacting with Team Leader for day-to-day work. Review project design drawings and provide direction, if need be, highlight potential technical problems and suggest means to resolve the same in consultation with PIU.
- Witness, provide advice and assistance on start-up, testing and commissioning as per detailed specifications and contract conditions
- To update the team and Client in case of foreseeable issues & hindrances which could impact the progress of the projects as per the approved plan
- To inspect the works, during the construction period and during the Trial run and at proper interval
- To review progress reports submitted by the contractor and prepare weekly, monthly progress reports highlighting the bottlenecks
- Establish a system of Quality control & Quality Assurance of works, approve materials, concrete mix designs, sampling and testing procedure and ensure implementation of the same on site
- Guiding / Supervision for the necessary training /orientation program for the workforce for achieving better productivity of work
- Management And planning of construction activities
- Overall supervision of the construction activity and implementation of work as per design for various improvement of Water Supply Scheme of Nagar Palika parishad under Sarni
- Perform compressive test, slump cone test, material cube test, sieve analysis, JMR signed Hydro test etc
- Responsible for day-to-day site and office work of domain engineering as per plan
- Evaluate BOQ/Tender drawings and preparation of budgets, tendering & Drawings
- Responsible for execution, supervision, co-ordination, monitoring and scheduling of construction activities
- Finalizing of work program, resources on daily and monthly basis and closed review of the same on daily basis
- Construction Supervision and Quality Control of contractor's site activities
- Quality maintains according to drawing and specification
- Supervision of 75 mm to 315 mm dia. HDPE pipe & 300 to 400 mm dia. DI K-7 distribution system pipe laying work
- Supervision 150mm to 500 mm, Dia. K-9 Clear Water Rising Main Pipe Laying work
- Supervision of Raw Water Rising Main 500 Dia. DI K-9 Pipe Laying work
- Testing of material, Cube Test, Impact Value Test, Sieve Test, Water Absorption Test, Slump Test done at lab at field time to time
- Supervision of BT Road Restoration and CC road restoration work
- Supervision of OHTs of 300KL,1000KL, & 1500 KL work
- Strictly monitor the progress of work for timely completion of the project
- Prepared contactor's bill
- Supervision of Sluice valve, Air valve & Scour valve, NRV, Butterfly Valve, chamber, construction work
- Supervision of DI 150mm to 500mm dia pipe line Thrust block work
- Supervision & Construction of WTP 20 MLD & Intake well 23 MLD
- Co-ordination with, Contractors & Clients
Site Engineer - P C Snehal Construction Pvt. Ltd. - Bhavra Nagar in Alirajpur District
(2018-05 - 2021-03)
Execution of water supply scheme including Intake Well, Water Treatment Plant (WTP), Over Head Tank (OHT), Rising Main and Distribution Network as per approved drawings and specifications. Execution of 150 KL capacity Over Head Tank with 16 m staging height including reinforcement, shuttering, concreting and curing works. Execution and commissioning support of 1.60 MLD Water Treatment Plant including treatment units, filtration system and pumping system.
- Execution of Raw Water Intake Well along with installation of pumping machinery and associated RCC structures
- Execution of Raw Water and Clear Water Rising Main pipeline works using DI K-9 pipelines
- Execution of HDPE distribution pipeline network including 110 mm to 250 mm dia pipelines
- Execution of valve chambers, thrust blocks and allied civil construction works related to pipeline system
- Execution of electrical works including transformer installation and HT line work
- Assisting in installation of electromagnetic flow meters and PLC-SCADA system
- Ensuring work progress, quality control and execution as per project schedule
- Executed Raw Water Rising Main using 150 mm dia DI K-9 pipeline including laying, jointing, alignment, testing and commissioning
- Executed Clear Water Rising Main using 150 mm and 200 mm dia DI K-9 pipelines including laying, jointing and testing works
- Executed HDPE distribution network including 110 mm, 140 mm, 160 mm, 180 mm, 200 mm and 250 mm dia pipeline laying and jointing works
- Executed Over Head Tank structural works including reinforcement, shuttering, concreting and curing
- Executed Water Treatment Plant construction including civil works, filtration system and pumping system installation
- Executed Raw Water Intake Well construction and installation of pumping machinery
- Executed valve chambers, thrust blocks and allied civil construction works
- Executed electrical works including transformer installation and HT line work
- Conducted field and laboratory tests including slump test, cube test, sieve analysis and water absorption test
- Maintained site records, measurement books and assisted in preparation of contractor bills
- Coordinated with subcontractors, site team and client representatives during execution of work
- Monitored daily site progress and ensured timely completion of project
Site Engineer - Om Construction Company, Tikamgarh - Panna (M.P)
(2015-05 - 2018-05)
Material Testing and Checking sites on regular basis. Perform compressive test, slump cone test, material cube test, etc. Responsible for day- to- day site and office work of domain engineering as per plan.
- Evaluate BOQ/Tender drawings and preparation of budgets, tendering & Drawings
- Responsible for execution, supervision, co-ordination, monitoring and scheduling of construction activities
- Finalizing of work program, resources on daily and monthly basis and closed review of the same on daily basis
- Construction Supervision and Quality Control of contractor's site activities
- Quality maintains according to drawing and specification
- Execution of 90 mm to 160mm dia. HDPE pipe laying work
- Execution 400mm Dia. Clear Water Rising Main Pipe Laying work
- Execution of Raw Water Rising Main 600 Dia. K-9 Pipe Laying work
- Testing of material, Cube Test, Impact Value Test, Sieve Test, Water Absorption Test, Slump Test done at lab at field time to time
- Execution of BT Road Restoration and CC road restoration work
- Execution of OHTs of 100KL to 300KL work
- Strictly monitor the progress of work for timely completion of the project
- Prepared contactor's bill
- Execution of Sluice valve, Air valve & Scour valve chamber construction work
- Execution of DI 200mm to 500mm dia pipe line Thrust block work
Site Engineer - Laxmipati Balaji Infrastructure India Pvt. Ltd - Vidisha (M.P)
(2014-04 - 2015-04)
Checking sites on regular basis. Material Testing. Perform compressive test, slump cone test, material cube test, etc. Responsible for day-to-day site and office work of domain engineering as per plan.
- Responsible for execution, supervision, co-ordination, monitoring and scheduling of construction activities
- Finalizing of work program, resources on daily and monthly basis and closed review of the same on daily basis
- Execution of works of quality maintain according to drawing and specification
- Execution of 90 mm to 160mm dia. HDPE pipe laying work
- Execution 400mm Dia. Clear Water Rising Main Pipe Laying work
- Work of Raw Water Rising Main 600 Dia. K-9 Pipe Laying
- Testing of material, Cube Test, Impact Value Test, Sieve Test, Water Absorption Slump Test done at lab at field time to time
- Execution OHTs of 100 KL to 400 KL work
- Execution of BT Road
- Execution of BT Road Restoration and CC road restoration work
- Strictly monitor the progress of work for timely completion of the project
- Prepared contactor's bill
- Execution of works of Bitumen Road and CC road
- Execution of MS and GI pipe laying work
- Execution of DI pipe line laying work
Site Engineer - Om Construction Company Tikamgarh MP (India) - Tikamgarh (M.P)
(2013-06 - 2014-03)
Responsible for overall construction quality assurance, Testing and administration of the contracts under the project. Project Management, Co-ordination with client & Contractor and Measurements & R.A. Bill Checking. Construction of OHTs, HDPE distribution Network, and Feeder main DI water line.
- Inspect project sites to monitor progress and ensure conformance to design specifications and safety or sanitation standards
- Direct construction, operations, and maintenance activities at project site
- Direct or participate in surveying to lay out installations and establish reference points, grades, and elevations to guide construction
- Estimate quantities and cost of materials, equipment, or labour to determine project feasibility
- Test soils and materials to determine the adequacy and strength of foundations, concrete, asphalt, or steel
- Material Testing
- Perform compressive strength test, slump cone test
- Responsible for day-to-day site and office work
- Responsible for execution, supervision, co-ordination, monitoring and scheduling of construction activities
- Finalizing of work program, resources on daily and monthly basis and closed review of the same on daily basis
- Strictly monitor the progress of work for timely completion of the project
- Construction Supervision and Quality Control of contractor's site activities
- Execution of works of quality maintain according to drawing and specification
- Execution of works of Bitumen Road and CC road
- Execution of MS and GI pipe laying work
- Execution of DI pipe line laying work
- Testing of material, Cube Test, Impact Value Test, Sieve Test, Water Absorption Test, Slump Test done at lab at field time to time
- Perform compressive strength test, slump cone test, material cube test, etc
- Responsible for execution, supervision, co-ordination, monitoring and scheduling construction activities