Land Surveyor: KOON CONSTRUCTION & TRANSPORT PTE LTD, Since January-2015
- New Road Connection at Seletar Link & Widening of TPE between Jalan Kayu and Punggol West Flyover, Since July 2019 (LTA Project ER 507A)
- Infrastructure works at Seng Kang West from April 2017 - June 2019. (JTC Project)
- Land Preparation Works for Changi Airport Terminal 5 from January 2015 to March 2017. (MOT Project)
Land Surveyor: Jurong Primewide Pte Ltd., March 2012-December 2014
- Construction of MRT Depot -Tuas West Extension (LTA Contract No: C1685)
Job Responsibility:
- Organizing and managing daily survey activities in project sites, monitoring and guiding junior surveyor’s work.
- Coordinate with consultants, site Engineers and Project Team for Setting Out works.
- Setting out for Pile, Pile cap, sub-structure, Super structures, Column, Beams, Crosshead, deck slabs.
- Setting out alignment and elevation for all sub-structure, Super structures.
- Setting out road alignment and level for Subgrade, Sub base, Base course and Asphalt.
Sub base, Sub-grade, Culverts, drainages and other Concrete Structures.
- Setting Out works for Horizontal alignment, Culverts, drainages and other Concrete structures.
- Coordinated timeframes betweenteams and team members to ensure survey works are meet the project requirements.