PeriodEmployerPosition HeldProject/ ActivityDuration (Months)May 2019-June 2019 Ministry of Transport- Material Testing and Research Department-Coast RegionInternDuties:
- Soil Testing- Atterberg’s limit tests (LL, PL and LS & PI)
-Compaction tests
-CBR test
- Aggregate tests – Grading, FI, ACV, LAA and SSS
- Concrete Testing – Casting and crushing concrete cube
- Pre-mix Analysis of Bituminous materials
- Concrete Design
2 July 2019- March 2020Associated Construction Co. Ltd
Upgrade to Bitumen Standards of Jomvu kuu -Jitoni – Rabai
Site Office Rabai,
Assistant Site Engineer/Intern-Daily supervision of works which included: earthworks, pavement works and concrete works
-Working closely with material technician to check quality of materials and work done by contractor through laboratory tests and field tests
- Keep records of Materials on site and daily material consumption
-Liase with the Resident Engineer’s team on matter pertaining inspections of works and supervision.
7April 2020-March 2023Kenya Roads Board,
Seconded to:
Kenya Urban Roads Authority
Assistant EngineerDuties
- Carrying out detailed engineering design of roads and minor road structures:
The design aspects included detailed traffic survey, alignment soil and geotechnical investigations, borrow pit material testing, detailed topographical survey, geometric and pavement design, preparation of Engineering design reports, quantity/cost estimation and preparation of tender documents.
- Construction of Kisumu Eastern Ring Roads- 25 km
- Construction of Kabarnet Town Roads-20km
- Construction of Access to Infinity Industrial Park Phase III- 4 km
- Development of Wajir Town Roads-30 km
- Construction of Eldas Township Roads-25 km
- Construction of Garsen Town Roads-10 km
- Construction of Habaswein Town Roads-17 km
- Construction of Kitengela Bypass and Acacia Road- 15 km
- Design Review of Access to Creek Village, Mshomoroni- 1.9 km
- Construction of Utawala Town Roads-15 km
- Construction of Kitale Bypass 15Km
- Design Review of Dualling Ngong Road Phase IV 8.5 Km
- Dualling of Limuru Road
- Dualling of United Nation Avenue
Duties:
- Material testing which included alignment and material site soil testing
- Traffic studies
- Topographical survey
- Geometric and pavement design
- Preparing design report
14(Design office)
- Assistant Engineer in the design and supervision of the following project:
- Construction of Kwale and Ukunda Township roads -5 km
- Construction of Kibera- Langata Road (Missing Link Lot 1)-2 km
- Construction of Eldas Township Roads-7.5 km
Duties:
- Design review and appraisal
- Drafting site instructions for approval by the Resident Engineer
- Assisting in keeping all site records
- Assisting in preparation of monthly progress reports
- Assisting in confirmation of measurements of works
- Assisting in control of quality of works
- Review of contractor’s statutory documents and respond as instructed by the resident Engineer.
- Any other assignment given by the Resident Engineer from time to time
18(project supervision and contract management) Assisting in office duties in the Directorate of Urban Roads development (Special Projects)
Duties:
- Checking the Contractor’s Interim Payment Certificates (IPC) for confirmation of the entered and submitted quantities and subsequent certification for submission to the Engineer.
- Checking of adequacy of Insurance cover and Advance payment guarantees for newly awarded contracts.
- Attendance of site meetings and preparing the minutes thereof.
- Evaluation and analysis of the Contractor’s claim reports before submission to the Engineer.
- Assisting in other contract management & supervision duties
28