Highly professional and talented civil engineer is looking for a challenging position where I can maximize my experience and develop my skills while making a significant contribution to the success of the company.

الخبرة

Estimator May 2021 - Present

Civil and Scape, Australia (Working from Lebanon)

Prepared detailed quantity takeoff for different civil and landscaping works (soft works - hard works)

Estimated material, labor, equipment and other miscellaneous costs

Provided pricing and cost breakdowns for change orders

Gathered quotes from sub-contractors and suppliers

Sent Request for Information for clients to clarify different queries

Identified scope and created quotations with inclusions/exclusions

Civil Engineer / Quantity Surveyor Mar 2020 - Present

Freelance

6&8 Parramatta Square Project (Australia) (March 2021)

Quantity Takeoff for landscaping, construction and infrastructure work

EDSA Power Plant (Sierra Leone) (October 2020)

Quantity Takeoff for RC Works and finishing

Material Takeoff

Steel Furnace Warehouse (Cameron) (September 2020)

Quantity Takeoff for Earthworks for 20,000 m² warehouse (excavation and backfilling)

Restoration of an old Building (Lebanon) (May 2020)

Supervised Structural Works for Columns (Concrete Jacketing – Steel Jacketing)

Supervised Finishing Works (Plaster–Tiles–Pipe Replacement–Doors …)

Supervised Concrete Tests

Quantity Takeoff for Executed Works

Prepared Invoices for Subcontractors

Quantity Surveyor Aug 2016 - Feb 2020

Cooperativa Muratori & Cementisti di Ravenna, Lebanon

GBWSP is for the construction of a series of tunnels around 23 km to convey water from the existing hydroelectric power system tunnel near the village of Joun, some 30 km south of Beirut,

to Khaldeh.

Beyond

Khaldeh comes a twin pipeline around 9 km to convey water to the site of proposed reservoirs at south of Beirut. GBWSP project value is around 200M dollars funded by the World Bank in which the contract is the Bank Harmonized Edition of FIDIC 2005.

Quantity Takeoff for different items in the BOQ based on CESMM3 including earthworks using CIVIL 3D

Prepared supporting documents for payment

Prepared monthly payment

Prepared estimates for payment as well as subcontractors' payments

Monitored and verified payments for different subcontractors

Prepared cash flow forecast

Prepared variation orders

Calculated new rates in BOQ

Prepared Revenue Vs Cost Comparison tables for some BOQ items

Prepared comparative tables for value engineering

Assisted in preparation of supporting documents for Claims

Assisted in estimation for new tenders

Civil Engineer Sep 2015 - Jul 2016

AL-Masar Trading & Contracting Company, Lebanon

Supervised civil ,construction and finishing works to ensure that the work done is as per the project specifications and approved drawings

Supervised renovation of an ancient building

BOQ Preparation for different works

Prepared Invoices for Subcontractors

التعليم

ME in Construction Engineering and Management 2022 - Present

American University of Beirut, Lebanon

BE in Civil and Environmental Engineering 2011 - 2015

Beirut Arab University, Beirut, Lebanon