Site Manager of The HIVE Tower at Eko Atlantic, Victoria Island at ARKLAND Group- ASL Contractors LTD (2026-03 – Present)
- Project Lifestyle Management: overseeing projects from pre-construction through to final close-out, including scheduling, milestone tracking and resource planning.
- Field Coordination: supervising on-site supervisors and subcontractors to ensure work adheres strictly to blueprints, local building codes and safety regulations.
- Risk & Quality Control: implementing proactive safety protocols and conducting regular quality inspections to mitigate project risks and defects.
- Reporting: providing weekly progress updates and financial health reports to the Leadership team.
Field & Technical Coordinator: Education project funded by AICS (1.7 million USD) at We World-GVC (2018-12 – 2026-03)
- Construction of 2 additional floors (400 sq.m each) and structural elements.
- Full implementation of electrical, mechanical, plumbing, and fire alarm systems.
- Architectural works including plastering, tiling, waterproofing, carpentry, aluminum, and painting.
- Managed the installation of solar systems in eight schools, covering steel structures, PV panels (total of 114 panels), lithium batteries, and protection systems.
- Reviewed and supported the preparation of technical designs, drawings, structural details, BOQs, and cost estimations.
- Contributed to tender preparation, technical evaluation, awarding, and supervision of contractors.
Wash engineer: Water Network supply funded by the EU (1.2 million USD) at We World-GVC (2018-12 – 2026-03)
- Supervised the full implementation of water network projects in Qatlabeh and Akroum villages, covering borehole drilling (total of 927 m.b.g.l), construction of pumping stations with all the related mechanical items such as boosters and submersible pumps, in addition to the construction of reservoirs (total of 1000 cu.m), and rehabilitation of spring catchments, and laying of water pipelines (total of 25 km).
- Monitored and ensured material quality control for concrete works, base course, and sub-base layers, verifying compliance with technical specifications and standards.
- Oversaw on-site construction activities, ensuring adherence to project designs, safety procedures, and timelines, including concrete works for the pumping station building, and conducted concrete crushing, slump, and reinforcement bar tests.
- Coordinated with contractors, suppliers, and engineers to ensure proper material testing, mix design approvals, and quality documentation.
- Prepared site inspection reports and provided technical feedback to address deviations or non-conformities during implementation.
Field Supervisor at Danish Refugees Council (DRC) (2018-06 – 2018-12)
- Supervised the full implementation of a road construction project (2 km), ensuring compliance with design specifications, safety standards, and approved schedules.
- Monitored material quality control, verifying the use of approved materials such as sub-base, embankment, base course, and asphalt.
- Conducted and supervised field and laboratory tests, including Troxler compaction tests, California Bearing Ratio (CBR), and sieve analysis, to ensure material quality and proper layer compaction.
- Coordinated with contractors and site engineers to resolve technical issues, verify test results, and ensure corrective actions where required.
- Prepared site inspection reports and maintained quality assurance records throughout the project implementation.
Project Supervisor at Solidarités International (2016-08 – 2017-12)
- Project Supervision: Supervised the construction of latrines, septic tanks, manholes, and canals in refugees' informal settlements, ensuring quality and adherence to project specifications.
- BOQ Preparation: Prepared Bills of Quantities (BOQ) for construction projects, detailing material, labor, and cost estimates.
- Field Assessments: Conducted site assessments using the KOBO App to gather and analyze data for project planning and monitoring.
- Quality Control: Ensured construction activities met safety and quality standards, conducting regular inspections and addressing any issues promptly.
- Stakeholder Coordination: Collaborated with project managers, engineers, and local stakeholders to facilitate project implementation and resolve challenges.
- Progress Reporting: Documented and reported construction progress, providing detailed updates to senior management and donors.
Civil Engineer - Highway and Bridge Construction at DAR-AI-HANDASAH (2009-11 – 2014-08)
- Highway Construction: Supervised and managed the full implementation of a 150 km-long, 45 m-wide highway, connecting N'zeto and Soyo, ensuring adherence to design specifications, safety standards, and project timelines. Oversaw all phases of work, including earthworks, paving, and infrastructure development, with a focus on quality control, materials compliance, and resource optimization. Directed the installation of box culverts, pipe culverts, and advanced drainage systems to ensure long-term durability and efficient water management.
- Bridge Construction: Led the construction of (8) eight major bridges, each with an average length of 200 meters, managing all structural and geotechnical aspects. Supervised the execution of 1,100 piles and 18 pile load tests, coordinating closely with design and quality assurance teams to guarantee structural integrity, proper materials selection, and compliance with ASTM and International standards.
- Pre-Stressed Bridge Construction: Oversaw the complete construction of a 500 m-long pre-stressed concrete bridge spanning a river (M'BRIDEGE), from foundation works to deck launching. Implemented rigorous materials inspection and testing procedures to verify compliance with international structural, safety, and environmental standards, ensuring optimal performance and durability.