QC INSPECTOR
Feb 2021 - Apr 2023
UNITED ENGINNERING SERVICE (UES), MUSCAT
- Preparation of Inspection Schedule according to ITP
- WHR preperation.
- Material Receiving Inspection and preperation of MRIR.
- Vessel Shell plate Inspection after rolling.
- Electrode handling and Welding Parameter Inspection.
- Inspection of dish head to shell plate fit up of a Vessel.
- Inspecting Long seam and Circumferential seams of vessels.
- Vessel Nozzle Opening Inspection.
- Vessel nozzle and manway fit up inspection.
- NDE as per ITP and RT film review.
- Visual and Dimensional Inspection of vessels, tanks, piping and skid.
- Post weld heat treatment inspection
- Hydro Test Inspection.
- Factory Acceptance Test Inspection.
- Punch point close out inspection.
- MRB preperation.
- Inspection of piping- system wise and confirm it is according to P & ID
Diagram, Isometric drawing and
- GA drawing.
- Before Fabrication, Erection to check the isometric drawing with corrects revision as per the latest
- record.
- Monitoring and Inspection of Erection Activities of Piping Spool as per drawing, Coordination of QC
- activities with Client, construction department in all stages of the process to avoid unnecessary delay
- for the easy execution of work.
- Weld Joint Inspections Including Fit-ups, Visual Inspection of Pipelines
- Making sure baking of electrodes and material handling.
- Inspection of pipeline for it's alignment, primary welding, line coordination, valve installation etc
- before hydrotest and making sure all the A punches are closed.
- Conducting Reinstatement line walk and making sure all the primary and secondary punches are
- closed.
- Inspection of steam tracing of pipes.
- Preparation of Hydro Test Package documents for approval from client.
- Inspection of hydrotest, making sure all the gauges are calibrated, all the weld joints are exposed, all
- the flanged joints are installed with proper gasket and bolts and making sure the pressure is not
- decreasing during pressure holding time.
Welding supervisor
Sep 2019 - Feb 2021
Galfar Engineering & Contracting SAOG, MUSCAT
- Planning of daily activities.
- To make sure the availability of materials with the workers to complete the work.
- To report the site engineer before and after the completion of preparation and welding of each joint.
- Keeping the daily progress reports.
- Supervising NDT team for Daily Inspection and allocating according to the requirement
- Preparing work permits for ND work, conducting safety toolbox talk.
- Witness/Review all types of N.D.T. work as per client requirement.
- Implementing safety requirements during welding inspection / NDT as per
Company safety requirements.
6G WELDER
Galfar Engineering & Contracting SAOG, MUSCAT
- Worked in YKP project as a pipe welder.
- Worked in OMC project as a pipe welder.
Jun 2017 - Sep 2019