Project Planner/Scheduler at EDC Energy Development Corporation (2022-09 – 2023-09)
Projects: 20MW Geothermal Power Plant, Sorsogon, Philippines
- Prepared and developed tender work schedule as per contract.
- Integrate the various package schedule into one over-all master schedule.
- Prepared manpower histogram, update the work schedule and adjust if needed. Recovery decisions.
- Prepared and update progress report. Coordinate to the contractor's manager and site supervisor and other support groups. Evaluate contractor's progress claims. Reporting to the stakeholders.
- Update the resource manpower schedule, equipment, materials and coordinate with the project team.
Planning Engineer at Daewoo E&C Papua Indonesia (2020-01 – 2021-01)
Projects: BP Project, Tangguh Expansion Project
- Prepared and developed Master Schedule Plan.
- Prepared manpower histogram, developed schedule and adjustment if necessary.
- Prepared and update progress report. Coordinate to the site supervisor and other support groups.
- Updated the resource schedule manpower and equipment, coordinate with the clients and interfaced with the project team. Manage, control and monitor manpower at project site.
Planning Engineer at RPD Construction Inc. (2018-05 – 2020-01)
Projects: Building and Ground Maintenance, PSPC Pilipinas Shell Petroleum Corporation, Shell Refinery, Tabangao, Batangas City, Philippines
- Defined scope, Interpret designed drawing and initiated planning system.
- Prepared work schedule in Primavera P6 and made projected adjustment if necessary.
- Insured accurate data and cost estimates and resource leveled.
- Coordinate with the clients and interfaced with the project team.
Planning/Scheduling Engineer at Atlantic, Gulf & Pacific Company of Manila Inc. (2017-03 – 2017-11)
Projects: Lycopodium and LOBP Petron Project, Building Structural Steel.
- Prepared progress report and S-curve diagram. Insured project completed on target delivery schedule.
- Defined, Interpret designed drawing and initiated planning system.
- Prepared work schedule in Primavera P6 and made projected adjustment if necessary.
- Insured accurate data and cost estimates and resource leveled.
- Coordinate with the clients and interfaced with the project team.
Planning Engineer at Al Zamil Heavy Industries Inc. Ltd (2013-08 – 2015-09)
Projects: Large and Heavy High Pressure Vessels and Tanks
- Defined scope, prepared WBS and interpreted designed drawing
- Developed Master Schedule Plan in Primavera P6 and analyzed known and unknown risk.
- Increased work efficiency, actual site monitored, achieved the project completion base on target delivery schedule. Insured adequate and accurate project report and developed data of specific system.
- Interfaced, coordinated to the project team feed the new development data and top priorities.
Planning Engineer at STX Heavy Industries Inc. (2010-10 – 2012-11)
Projects: IGD-5, Hyundai Project, Habshan- 5 utility offsite
- Defined scope, planned and updated work schedule and tracked in S-curve diagram
- Site actual evaluated against work schedule plan, Increased work efficiency.
- Prepared and updated the resource schedule manpower and equipment.
- Controlled and managed the actual result versus Plan and completed the project on target schedule.
- Ensured accurate data and developed and updated look ahead and weekly plan.
Planning Engineer at MMHE Malaysian Marine and Heavy Engineering (2009-01 – 2010-01)
Projects: Tangga Barat Oil & Gas Platform Project.
- Defined scope, planned work schedule
- Site monitored, updated actual accomplishment and tracked in the progress system versus plan.
- Initiated site schedule, priorities implemented, interfaced and collaborated at site project team.
- Prepared progress report and S-curve diagram, analyzed critical path to be prioritized.
Planner/Scheduler at Atlantic Gulf & Pacific Company of Manila Inc. (2006-03 – 2009-01)
Projects: Oil & Gas Project and Goro Nickel Mining Project at Noumea, Caledonia.
- Interpret designed drawing, reviewed scope of work, Prepared and developed the resource loaded schedule.
- Prepared and developed and incorporate multiple schedule plan to Master Schedule Plan. Critical path analysis and task priority.
- Monitored the actual accomplishment for progress report. Performance measurement or KPI's.
- Coordinate with project management team, and work closely with the client. ensured data accuracy of the project scheduling, execution and reporting.
Project Planning and Control Engineer at Aboitiz Construction Group Inc., Metaphil Division (2004-01 – 2005-09)
Projects: 5MW New Washington Diesel Power Plant and New Slipway II, (THICI) Tsunishi Fabrication Shipyard.
- Defined scope, planned schedule and 2 weeks look ahead.
- Prepared S-curve diagram, tracked actual cost against budget plan and the projected cash flows.
- Insured adequate and accurate project report and developed data of specific system.
- Managed and controlled actual cost not over the budget cost and completed the project on schedule.