Construction Control Representative - US Department of Interior/Bureau of Reclamation - Pueblo, Colorado
(2023-09)
Contract assurance between the Department of Reclamation and the contractor.
- Attend progress meetings regularly.
- Track, inspect, and report daily production.
- Ensure safety procedures are followed.
- Monitor and ensure all phases of pipeline construction meet the required specifications from the installation of the pipelines to the cathodic protection and hydro testing.
- Collaborate with the design team to ensure correct implementation of design changes.
- Collaborate daily with the contractor to ensure construction schedules stay on track.
- Monitor all phases of construction on the AVC Project from pipe lay to the construction of the injection site.
Construction Control Representative - US Department of Interior/Bureau of Reclamation - Stockton, Kansas
(2022-10 - 2023-09)
Contract assurance between the Department of Reclamation and the awarded contractor.
- Attend daily and weekly progress meetings.
- Track, inspect and report daily production of Webster Dam Project.
- Assurance of Safety procedures are followed.
- Ensure design changes are accurately implemented with the design group.
- Meet with Dam operators to schedule Construction Operations with Dam maintenance.
Civil Inspector - US Department of Interior Bureau of Reclamation (Employed through CNS) - Altus, Oklahoma
(2022-02 - 2022-08)
Contract assurance between the Department of Reclamation and Odin Construction Solutions Inc.
- Ensuring contract excavation and contract elevations are correct through inspection
- Excavation of materials
- Compaction of earth materials
- Excavations of existing rock fill
- Erosion control Placement of impervious materials
- Placement of rockfill on face of dike
- Placement of gravel surfacing
- Placement of top soil
- Seeding and soil supplements
- Safety and safety monitoring
- Daily, weekly and monthly reporting
- Daily production confirmation
- Safety
- Daily reporting
- Equipment checks of all incoming equipment
- Documentation of all equipment and personnel on site daily
- Daily work plan meetings with contractor team
General Contractor - General Contractor - Murfreesboro, TN
(2021-01 - 2022-02)
- Bidding and contract small jobs for residential excavations
- Excavating
- Rock
- Waterlines
- Electrical
- Building Pads
- Bidding and contract commercial excavations
- Excavation for commercial buildings
Project Manager - MD Energy Services LLC - Weatherford, TX
(2017-12 - 2021-01)
- Managed pipeline and earthwork projects from start to completion
- Bid all projects
- Interview and hiring of all personnel
- Monitored safety regulations and programs
- Daily Communications with all oil and gas companies involved
- Oversee the daily routines and every aspect of each project from beginning to end
Project Manager - Arnold's Seeding/U.S. Pipeline - Wheeling WV
(2017-08 - 2017-11)
- Managed aerial hydro seeding and ground crew
- Oversee daily safety inspections of helicopters and ground crew equipment
- Managed production and staff
- Organized and ran daily meetings with involved gas companies to report production, safety and projected targets
- Review plans and specifications to develop construction procedures to meet the expectations of our customers
President - MS Pipeline - Odessa, TX
(2012-03 - 2017-07)
- Develop and maintain client relationships
- Provide Leadership necessary to set the standard of project service delivery
- Ensure pipeline and facilities work being constantly accurate and of high quality, in accordance with project management processes and procedures
- Oversee the ongoing development and consistent application of pipeline, facilities and programs
- Lead and assist with project bid proposals
- Identify equipment requirements for all pipeline projects
- Provide leadership in safety excellence, ensuring compliance with client safety programs, corporate safety programs and OH and S legislation
- Mentored and guided the pipeline team in establishing goals, recruitment, performance evaluations and planning
- Monitor all profit and loss within the management team
- Inspect all phases of pipeline construction
Pipeline Superintendent - Various Companies
(2000-06 - 2012-02)
Superintendent for various pipeline companies throughout the United States
- Oversee and participate in all phases of pipeline construction including
- Planning, installation, right of way construction through the final tie-ins
- Post job reviews
- Review plans and specifications to develop construction procedures to meet the expectations of our customers
- Develop and monitor construction schedules
- Track man hours, equipment usage and schedules to manage and control costs
- Hire and supervise employees and subcontractors
- Administer company safety programs for employees and subcontractors to direct safe and efficient job performance
- Coordinate with inspectors to ensure construction meets company, customer and government requirements
- Facilitate communication between landowners, community members, customers and companies.