Mark Weiss
Senior Construction Manager
Hire this person
Send a job offer directly to this candidate
About
Senior Construction Manager with extensive experience delivering large-scale civil, mining, industrial, and pipeline projects across Western Canada. Proven ability to lead multi-disciplinary teams, manage complex construction sequencing, and maintain strict commercial controls on projects ranging from $1M to $950M. Expert in field execution, risk mitigation, contractor performance management, and integrating engineering design with constructability requirements.
Recognized for stabilizing operations, improving schedule accuracy, and driving cost-aligned decision-making in high-risk, high-visibility environments.
Experience
Construction Manager - Elk Valley Resources
(2020-01 - 2025-01)
- Site F Dam Raise & Underdrains (2025) $8M: Directed all civil construction activities for a dam raise and underdrain expansion, ensuring compliance with engineering specifications and geotechnical requirements.
- Validated construction sequencing and optimized workflow to reduce equipment idle time and maintain production targets.
- Oversaw equipment utilization planning, operating hour budgets, and field-level cost controls.
- Managed commercial forecasting, daily LEM approvals, and contractor performance metrics.
- Collaborated with engineering teams to resolve design conflicts and confirm constructability prior to execution.
- Teck Coal Cover Project (2024) $950M Program / $65M Package: Supported feasibility assessments and constructability reviews for a multi-year, multi-discipline program.
- Provided technical input during design development to align engineering deliverables with field execution constraints.
- Assisted procurement with cost modeling, commercial forecasting, and package planning for a $65M scope.
- Teck Coal Dewatering Project (2023) $65M: Led civil execution for a large-scale dewatering infrastructure program, ensuring alignment with hydrological and geotechnical requirements.
- Conducted structured schedule reviews with contractors to validate progress, identify variances, and maintain critical path alignment.
- Managed commercial forecasting, LEM approvals, and field-level cost tracking.
- Coordinated multi-discipline contractors to maintain safe, efficient production.
- Teck Coal Wastewater Cells Development (2023) $3M: Oversaw mechanical pipe fusing, installation, and supporting civil works for a wastewater cell upgrade.
- Directed earthworks include HDPE installation, aggregate placement, erosion control, and excavation to embankment specifications.
- Supervised architectural and civil interfaces to maintain quality and compliance.
- Teck Coal Accelerated Reclamation (2023) $5M: Managed reclamation earthworks, equipment utilization, and production sequencing.
- Led commercial forecasting and contractor oversight to maintain cost alignment.
- Teck Coal Breaker/ROM Building Reclaim Water Supply (2023) $2M: Coordinated scheduling, equipment utilization, and crew deployment for a water supply system upgrade. Overseen Earthworks, mechanical and HDPE installation. Supported business development through strategic partnerships with client interaction and support with future direct award projects.
- Blackwater Gold Mine (2023) $10M Civil Package: Directed civil construction activities, production sequencing, and commercial controls for a major mining development.
- Enbridge Valve Station Expansion (2022) $1.5M: Led ground disturbance, damage prevention, and subtrade coordination for a station expansion project.
- Ensured compliance with pipeline integrity and safety requirements.
- Enbridge Drain Expansion (2021) $1M: Managed pond excavation, swale regrading, hardscaping, and environmental controls.
- Oversaw damage prevention and field safety compliance.
Project Manager - Various Contractors
(2016-01 - 2020-12)
- Nutana West Watermain Rehab Saskatoon, SK $6M: Managed 3000m of watermain replacement, service tie-ins, and full road restoration.
- Oversaw QA/QC, line locates, and damage prevention.
- 69th Avenue Museum Road Cold Lake, AB $4M: Managed clearing and grubbing, watermain fusing 2500 linear meters, ditch excavation, culvert replacement, road construction and erosion control.
- Managed excavation to embankment and QA/QC compliance.
- SaskPower Fire Hydrant System Refurbishment Coronach, SK $2.5M: Managed installation of pre-krete lined pipeline, excavation, welding, and hydrant refurbishment and installation of Post indicator valaves.
- Oversaw line locates, damage prevention, and QA/QC.
- Macklin Press Avenue Macklin, AB $3.5M: Delivered 2500m of sewer main, manholes, services, and auger bore crossings.
- Mosaic Cluster 35–38 Pipeline — Belle Plaine, SK — $9M: Managed 2100m of gravity 350mm pre-krete lined pipe installation, welding, pipe coating, tie-ins, reclamation, hydro testing and QA/QC.
- John Paul Access Road Stony Plain, AB $3M: Oversaw installation of water, sewer, storm, and site services for a new development. Earthworks included site grading road construction and lot grading.
- Managed road construction, line locates, and QA/QC.
General Superintendent - Graham Construction, Hamm Construction, Site Energy
(2008-01 - 2016-12)
Projects ranging from $1M–$28M across civil, industrial, and municipal scopes
- Directed field operations for civil, industrial, and municipal projects ranging from $1M–$20M.
- Led project planning, schedule development, and subcontractor coordination.
- Ensured compliance with OH&S, environmental requirements, and corporate safety programs.
- Managed labour, equipment, and material cost controls with monthly forecasting.
- Led pre-construction, progress, and stakeholder meetings to maintain alignment and resolve issues.
- Oversaw deficiency management, commissioning support, and project closeout.