Impart my knowledge in planning operations to ensure better performance in the area of managing and control schedule regarding Engineering documents and procurements.
Planning Engineer (E&P) at PETROJET Company. (Jul.2022 – Present)
procurement of all disciplines.
E&P Planning Projects:
Owner: ENI & AGIBA PETROLEUM
Contractors: -PETROJET COMPANY for Gathering and Export Pipeline
-Schlumberger for GTP
-Designing all necessary constructions, buildings, systems of all kinds (Process, Pipelines, ICT,
Equipment, …) including all required approvals from consultant.
-Supplying all the tasks related to mechanical works (Pipeline, ICT, ...), equipment electrical works,
Steel plates, metal structures, firefighting systems and automatic alarms
-Contract value: 500 million USD.
-Contract period: 12 months.
-Designing two parts of a 16" diameter diesel line from the docking station in Port Said to the Shahid
Ali Gamal station in Suez, also all buildings, systems of all kinds (Process, Pipelines, ICT, Equipment, …)
including all required approvals from consultant.
-Supplying two parts of a 16" diameter diesel line from the Raswa Station in Port Said to the Shahid
Ali Gamal station in Suez, also all the tasks related to mechanical works (Pipeline, ICT, ...), equipment electrical works, Steel plates, metal structures, firefighting systems and automatic alarms
-Contract value: 1.1 billion pounds.
-Contract period: 24 months.
-Designing of 22 Tank including all required approvals from consultant.
-Supplying all the tasks related to mechanical works (Pipes, ICT, ...), electrical works, Steel plates,
metal structures, firefighting systems and automatic alarms
-Contract value: 700 million pounds.
-Contract period: 36 months.
-Designing all necessary constructions, buildings, umbrellas and systems of all kinds, including all required approvals from consultant.
-Supplying all the tasks related to mechanical works (warehouses, pipes, ICT, …), electrical works,
equipment, metal structures, firefighting systems and automatic alarms
-Contract value: 627 million pounds.
-Contract period: 25 months.
EAST TO THE FUEL STOCKPILING PROJECT
-Designing of the cathodic protection system with 4 lines.
-Supplying all line supplies (cocks, elbows, tees and flanges) and cathodic protection supplies.
-Contract value: 61.7 million pounds.
-Contract period: 2 months.
Owner: EGYPTIAN PETROCHEMICAL COMPANY.
-Designing all necessary construction of a new soda unit of 350 tons/day for the Egyptian
Petrochemical Company.
-Supplying all the tasks related to mechanical works (warehouses, pipes, ...), electrical works,
equipment, metal structures, firefighting systems and automatic alarms.
-Contract value: 13 million pounds.
-Contract period: 19 months.
Structural Design & Technical Office Engineer at El-Hashimy Consulting Office.
(Aug.2021 – Jul.2022)
Design Responsibilities: (Exporting: Cad Drawings, Structure Design Model and Calculation Sheet).
Nile Development Company, the Tower Consists of 7 underground roofs (5 Podiums and
2 Commercials) and 36 Roofs with height about 130m designed according to ACI and
Reviewed, modified and valued.
Ministry of Egypt.
Ministry of Egypt.
Bridge Site Post Tension Engineer at The Arab Contractors. (Dec.2020 –Aug.2021)
Project: Light Railway Train "LRT" Construction of 10th of Ramadan Railway project –LRT
Owner: Ministry of Transportation. Consultant: Khatib & Alami. Contractor: The Arab Contractors.
The project consists of 11 stations with total length of 66 km Connects 10th of Ramadan to New Capital City.
Job Title: Project Site Engineer (in Post Tensioning).
Bachelor of Engineering: Civil Engineering (Oct.2014 - Jun.2019)
Ain-Shams University (Credit Hours System).
Designing of a Villa consists of 3 floors & Basement subjected to Axial Loads.
(Reinforced Concrete Project). Designing of a High-Rise building consists of 21 Floors (63m Height)