A Civil & Structural Engineering professional with a proven track record and in-depth knowledge and experience in developing and delivering large building construction projects. Over 23 years' experience with private sector consulting engineering practices in the UK on a wide range of new build and refurbishment projects in the commercial, residential, education, health, industrial, retail and leisure building sectors. Specific skills in the analysis and design of permanent works and temporary works for building structures.
Specific experience in Temporary Works and has worked as lead Temporary Works Engineer for Main Contractors and Demolition Contractors. Appointed as CRE for various projects to manage the work packages with Network Rail, TfL and DLR.
Experience
Lead TWC and Design Engineer - GALLDRIS Group - UK
(2026-01)
- Supporting Construction Teams on Design Issues and coordination of Design with external design consulting Engineers
- Responsibilities for rolling out a Temporary Works Management across Galldris Sizewell C Site Project Team
- Providing TW Design support to the needs of site team through design changes to manages minor changes that needs immediate reaction as onsite designer responsibility
- Working closely with permanent works designers, temporary works designers, and site teams to ensure solutions are practical, safe, and buildable
- Lead constructability reviews and contribute to construction methodologies and sequencing
Designated Individual - Tarmac CRH and Alun Griffith - UK
(2024-07 - 2025-09)
Provided structural design, temporary works design, Programming and project management services to Tarmac- Linford Project. Designated Individual for Alun Griffiths - Overview of compliance for the Temporary Works Procedures across all construction projects.
- Provides structural design, temporary works design, Programming and project management services to Tarmac- Linford Project
- Designated Individual for Alun Griffiths - Overview of compliance for the Temporary Works Procedures across all construction projects Alun Griffiths
- Tender support on Temporary works Scheme, buildability and cost estimation
- Design and Design-Checking of Temporary Works
- Responsibility for updating the Temporary Works Procedures and Forms to BS5975-2024
- Site visits and auditing of temporary works -Monthly
- Training of TWCs and TWSs. Leading and supporting the Regional Operation Directors
- Running of TW Forum -quartely for all TWC/Operation Directions and Project Managers
Regional Engineer - UK South - Sisk Group - UK
(2015-04 - 2024-06)
Temporary Works Trainer, auditor and designer. Undertaken CRE(Temporary Works) roles under the Engineering Management for Project standard NR/L2/INI/02009.
- Temporary Works Trainer for TW Coordinators and TW Supervisors – 2 Day Course on BS 5975:2019 and TW in-house Policies – SISK GROUP
- Auditing all Temporary Works Co-ordinators of all Sisk UK-South sites
- In house design of Temporary Works(Cat 0-3) for Sisk –UK South
- Undertaken CRE(Temporary Works) roles under the Engineering Management for Project standard NR/L2/INI/02009. Previous projects includes, CRE role on Peabody Estate, St John's Hill, Clapham Junction :2021 and CRE-D TW's role on Anthology-Deptford Foundry, Deptford: 2017. More recently;2022-2023 / CRE-D TW's role on Birmingham Health Innovation Campus project and Oxford Science Park Plot.
- Site Visit as appropriate to inspect temporary works installations for the Sisk Group
- Management and training of the Sisk Group Temporary Works Coordinators and Managers
- Coordination and management of Health & Safety matters associated with design scheme
- Work with the pre-construction team on tenders and present cost effective design solutions
- Meeting CDM requirement and reporting on lesson learned to Sisk Group
- Agreeing design fees, preparing contracts and engaging external design consultants
- Attend internal and external design meetings to suit clients and internal project teams
Structural Design Manager - Toureen Group - UK
(2013-12 - 2015-04)
Structural design and temporary works design for complex basement projects in London.
- V&A Museum Client- Wates – (78Million substructure package) – 3 levels of propping design/Double Basement and ground floor slab
- Furnival House – Façade retention and basement TW design and Sub structure works – Client Elmers - £54Million
- 20 The Boltons (£12Million) – Facade Retention with double basement. Internal structural alterations to inc Brampton Square (£15Million) – Design and Build Contract won in September 2014
- Henley on Thames (£5Million) – King Post earth retaining wall solution
- 35 Marylebone High Street (£20Million) – Design and Build Contract won in December 2014
- Shell and Asda – Tank installation /cofferdam design and installation
Senior Structural Engineer - KnappHicks and Partners - UK
(2011-11 - 2013-12)
Provides structural design, temporary works design and project management services to projects including schools, offices, residential and commercial buildings and referb projects. Scope of work varies from a small residential extension projects to large commercial steel frame building.
- Design of both temporary and permanent works to property developers, both in residential and commercial projects
- Projects varies from basement/retaining wall design, structural appraisal of buildings and value engineering various design schemes
Visiting Lecturer - University of East London - UK
(2010-02 - 2011-04)
Part-time lecturing role in Civil Engineering.
Civil & Structural Engineer - Bovis Lend Lease - UK
(2007-04 - 2011-06)
Major projects including St James Gateway, Athletic Village 2012 for Olympic Games, One Southampton Row, and Regent Place NEQ.
- St James Gateway (Client- British Land- 80 million) - Temporary works design coordination to ensure both stability of the building during construction stages. Designed and coordinated the substructure sequencing and design of temporary works for basement excavation and perimeter retention during construction
- Athletic Village 2012 - Stratford City (420 million) - Major new accommodation and open spaces for the London 2012 Olympic athletes and officials. Construction scheme, temporary works design during construction and engineering support to the site team. Provided leadership, management of the design through the construction stages to completion stage
- One Southampton Row (Client- M3C- 120 million) - Successful redevelopment of landmark site including demolition of the existing buildings, maintaining grade 2 listed façade. Complex temporary works design and coordination to ensure both stability of the excavation and the adjacent residential properties
- Regent Place NEQ - (Client- British Land- 160 million) - Key member of the bid team for the proposed high rise development and coordinated the design/ preconstruction phases with project team, engineers, architect and client
- Gloucester Quays and 240 Regent Place- (Client- British Land- 260 million) - Providing engineering assistance to facade retention schemes to heritage buildings and project temporary works assistance
Design Engineer - Chamberlain Consulting - UK
(2005-02 - 2007-04)
Provided structural design, advice and management of design team (engineers, draughtsman, and external consultants). Extensive use of finite element analysis design software.
- Projects included schools, offices, residential and commercial buildings and referb projects
- Windmill lane, Stratford (Client- Goldcrest Homes- 30 million) - Design Engineer, management of the design through the construction design proposal to CTRL to build over to construction stage. Two 9 storey residential building founded above the CTRL rail links to Stratford
- Schools and Referb Projects (Client- Tower Hamlet Schools) - Phase 2 town centre – Maidstone (£46m), new build [Bonner school PM House] and refurbishment for office blocks and processing plant ware house for Dagenham
Project Manager - Regis Design & Build Consulting - UK
(2001-01 - 2005-02)
Project Manager, designed various residential new build projects and project managed to successful completion.
- Worked closely with Building control and NHBC on various residential developments and reconstruction
- Care home development – Copper beach – Brighton
- Responsible for bid designs and advice and production of 'job winning' ideas for contractors on many design-build projects (The Royal Luton Hotel)
- Worked closely with the clients, architects, planners, construction teams and supply chain to consistently deliver individual projects to time and budget
- Created projects strategies and delivery plans to meet individual specifications
- Assembled, led managed and motivated multi-disciplinary project teams
- Provided detailed weekly and monthly reports for the clients and the Programme Manager
Research Assistant and Visiting Lecturer - University of East London - UK
(2001-03 - 2011-11)
Finite element analysis of Pipe Flange connection and tests for European Commission, with European country partners involved in the development of design code for Glass Reinforced Flange Design.
- Part time lecturer for Soil Mechanics, Auto CAD Programming and Lecturing on MSc module on Shallow/Deep foundation/Site Investigation and soil structure interaction
- Supervision and assessment of MSc research dissertations with restricted login
- Assisted and co-supervised BEng and MSc research projects within the subject area of Civil Engineering
Project Civil Engineer - Archirodon Construction Company - Cyprus
(1998-07 - 1999-09)
Vasilikos Offshore Power Station Project, Cyprus (Client – Electricity Authority of Cyprus- 20million CYP). Involved in the construction of Vasilikos Power Station Project.
- Planning and Construction of Cooling Water Pump house, intake and outfall structures
- Design/Construction of Control Room, Pigging station, Culverts and Onshore sleepers
- Engineered the installation of offshore 3x600m run of 2.8m diameter GRP pipes and intake structures connecting the Pump house
Site Engineer and coordinator - Karam Chand Tharpar & Bros (C.S) Ltd - India
(1996-10 - 1998-07)
Tunnelling landmark project for an underground PowerStation complex. Pykara Power Station Project, Tamil Nadu India.
- Site Engineer and coordinator for tunnelling landmark project for an underground PowerStation complex
- Responsible for structural analysis of shaft support steelwork
- Organizing and supervising day to day activities of the powerhouse complex construction
- Survey/Planning /Setting out the tunnelling of various underground structures such as shafts (both rising and sinking) for main Power House Complex for Pykara Hydro electric Power Station Project
Education
PhD - Soil Structure Interaction - University of East London (2001 - 2006)
MSc - Civil Engineering - University of East London (2000 - 2001)