Project Surveyor - M/s. L. B. Kunjir - Pune, Maharashtra, India
(2024-12)
Client: Maharastra State Infrastructure Development Corporation Limited. (MSIDC). Project: EPC Nipani - Talwade - Improvement and widening of Pimpalgaon Nipani – Talwade - Mahajanpur – Bhenadali – Karanjgaon Koture - Pimpri - Kundewadi - Nandurdi – Ranwad – Savargaon - Redgaon KhadakJamb to NH-03 Taluka – Niphad, District - Nashik on EPC Mode.
- As per following the Project Agreement in Schedule – B, ROW piller fixed on Ground from existing road center to both side.
- Establish BM, TBM points through Static Survey for highly accurate control points of EPC – Nipani Major District Road project. Make a schedule for traverse on all BM, TBM Controlling points.
- EPC – Nipani entire project Topography survey begins for Plan & Profile and the P&P submission to approval by the MSIDC.
- As per site condition where is necessary required to re-alignment, there is jointly record re-topographical survey and prepare realignment drawing in auto-cad, after that protocol wise record pre & post level in the entire project.
- Stakeout in total station surveying involves using a calibrate total station to accurately position physical points on the ground based on predefined co-ordinates for construction of Pavement Quality Concrete (PQC), Dry Lean Concrete (DLC), Granular SubBase (GSB), Minor Bridges, Box Culverts, HPC etc.
- As per following of the Typical Cross Sectional (TCS) drawing, prepare abstruct summary of execute quantity and after completion work record topographical as-built data in the entire project.
Sr. Project Surveyor - IRCON International Limited - Khulna, Bangladesh
(2018-10 - 2024-10)
Client: Bangladesh Railway. Construction of Khulna-Mongla Port New BG Railway line from Phultala to Mongla Terminal Station including Jetty line.
- Schedule and coordinate meeting for the survey management team for the entire project.
- As per the project alignment plan & Mouza map, fixed on ground ROW pillers, at present of client.
- Install BM, TBM controlling points within ROW, and make a schedule for maintain project alignment co-ordinates, so travers on all controlling points after 03 months interval in the entire project.
- As per site condition where is necessary required to re-alignment, there is jointly record topographical survey and prepare realignment drawing in auto-cad, after that protocol wise record pre & post level in the entire project.
- Stakeout in total station surveying involves using a calibrate total station to accurately position physical points on the ground based on predefined coordinates for construction of Major & Minor Bridges, Culverts, Building, approach Road of Station Building, Platforms, Track work, Level crossing - Gategoomty etc.
- For Railway's LWR Track work maintaining co-ordinates and levels as per the Plan & Profile, use controller Railway's Tamping machine (Plasser & Theurer – Unimat Series) in entire project.
- Prepare a Auto-cad drawing of Longitudinal Section and Typical Cross Section (TCS) and submission to client for approval.
- As per following of the TCS, prepare abstruct summary of quantity calculation and after completion of work record topographical as-built data in the entire project.
- Annexure wise prepare a microsoft sheet for 'Commissioner of Railway Safety' (CRS) / 'Government Inspector of Bangladesh Railway' (GIBR) of entire project including: List of Railway Stations, List of Major & Minor Bridges, List of Level Crossing Gates, Bridge Abstract, Details of Points & Crossing, Alignment Curvature Details, List of Grade and Formation Level, List of Railway Station Buildings, List of Passenger Platform Shed, List of Foot Over Bridge, Station Accommodation, List of Utility, BM
Senior Surveyor - M.K Gupta & CJJ Infraprojects Private Limited - Saraigarh, Bihar, India
(2018-04 - 2018-09)
Client: East Central Railway. Construction of Saraigarh to Nirmali New BG Rail line Project.
- Manage survey team and maintain sketch, maps, reports, construction data etc. skilled in verifying the accuracy of survey data, including measurements and prepare site working drawing in Auto cad.
- Install control points, maintain closed travers quarterly in a year, prepare co-ordinates list of project alignment and Pre-level record in entire project.
- Using a calibrate total station for topography survey and layout for Railway's Embankment, Formation, Bridges, Culverts, Approach roads, Platforms etc. in the project.
- Prepare a FRL excel sheet of Longitudinal section and chainage wise every 20m interval prepare cross section in auto cad and make a Abstruct summary of Earth work in filling & Cutting Quantity.
- Survey related all data with Quantity calculation sheet submit to the client for approval R/A bill submission.
- Protocol wise record joint measurement sheet for submission R/A bill to the client, and prepare same protocol for subagency's measurement against claim executed work bill process.
Project Surveyor - Bagmati Construction - Forbesganj, Bihar, India
(2016-01 - 2018-03)
Clients: IRCON International Limited, East Central Railway, WAPCOS Limited. Projects: Bathnaha (India) to Birat-Nagar (Nepal) New BG Railway Project, Forbesganj to Saraigarh BG Railway Project, ITBP 48 Battalion Camp in Katihar – Bihar.
- Manage survey team and maintain sketch, maps etc. skilled in verifying the accuracy of survey data, and prepare site working drawing in Auto cad for conducted survey sites.
- Maintain install control points travers quarterly a year. Jointly record pre level & post level for attachment of client bill submission purpose.
- Used a calibrate Total Station & Auto Level for Topography survey.
- Layout in construction of Railway's Embankment & Formation, Station Building, Platform, Culverts, VUP, Approach Road, ITBP Camp Buildings etc.
- Prepare drawing and list of Bar Bending Schedule (BBS) for construction of Buildings, Culverts, Vehicular Under Pass.
- Prepare executed work Bill with attached related supporting documents and submit to the client for approve R/A Bill.
Field Surveyor - DSR Surveys Private Limited - Yingkiong, Allahabad and Guwahati city
(2015-01 - 2015-12)
- DGPS used for Static Survey, Total Station used for Closed Traverse survey (N,E).
- Automatic Level used for Reduced Level travers, calculation of traverse, prepare list of control stations value and record topographical survey data, and draw in Auto cad topographical plan.
- Survey documents all are submitted to the client.
Surveyor - Dinesh Infraprojects Private Limited - Santaldih, West Bengal, India
(2009-10 - 2014-12)
Projects: (i) Construction of Bishnupur to Arambagh New BG Rail Line Project (Eastern Railway), (ii) Construction of Jharsuguda to Belpahar New BG 3rd Line Project (South East Central Railway), (iii) Adhunik Power & Naturals Resources Limited Thermal Power Plant Project (APNRL), (iv) Construction of Rampurhat to Pinargaria New BG Rail Line Project (Eastern Railway), (v) Construction of Sagardighi to Morgram New BG Rail Line Project (Eastern Railway), (vi) Construction of Sahibganj to Tinpahar New BG Rail Line Project (Eastern Railway), (vii) Construction of Ambika-Kalna to Jirat New BG Doubling Project (Eastern Railway), (viii) Santaldih Thermal Power Station Project (STPS)
- Manage all aspects of a large schedule of survey team in project and maintain sketch, maps, reports, construction data etc. skilled in verifying the accuracy of survey data, measurement, calculation and Auto cad drawing etc.
- Maintain traverse for controlling BM, TBM station 03 months interval entire project.
- Maintain project alignment or where is necessery require to realignment (as per site condition) of the project, there location draw a re-alignment drawing including curvature portion as per the RDSO specification, and submission to client for approval to working as on Re-alignment data.
- Protocol wise jointly record reduced levels before execution and record levels, measurement sheet after executed work.
- Make every chainage wise Cross Section in mm Graph sheet or Tracing graph roll sheet, and manual calculation for cross-sectional area, and prepare abstruct summary of Quantity, after that make client bill with attachment supporting documents and submit to client for approval.
- Stakeout in total station surveying involves using a calibrate total station to accurately position physical points on the ground based on predefined co-ordinates like Railway's Embankment, Formation, Minor Bridges, Culverts, Buildings, Platform, Road, Level Crossing, Height Gauge and in Thermal Power Plant Project's structure and CW, ACW Pipe, Makeup line Fabrication and Erection work.