) ( BLACK GOLD MUSEUM BGM PROJECT)
- Review drawings
- Lead the supervisors and foreman for site work
- Materials takeoff for all site work activities as per the approved materials
- Construction site work for (LIGHTING CONTROL LCP ,CBS )
- Construction site work for (FIRE ALARM , VOICE EVACUATION )
- Construction site work for (TELECOM )
- Construction site work for (ACCESS DOORS , CAMERA )
- Construction site work for (BMS )
- Coordinate with QC for inspections
- Following the procurement to deliver materials
- Use the available resources to achieve the target
- Coordinate with all disciplines ongoing work
2- Gulf co-operation symbol (GCS) since (11/3/2014 ) up to (1/5/2022)As
Senior Site Electrical construction Engineer ( KSA)
- 10 Schools Dammam project Superintendent Engineer (Feb 2022 up to now )
TBC Client
- Approval for Drawings
- Approval for Materials
- Lead and Coordinate with subcontractors for ongoing activities
- Reporting the ongoing activities
- Submitting invoices to Client
- Coordinate with testing and commissioning teams
- Work progress reporting
- Lead and Coordinate with Engineers at site
- Planning for the site work
- Managing the manpower
- Following up with supplier the delivery for materials
- Revising BOQ
- As built drawings
- MARJAN PROJECT (TCF PROJECT our client tecnicas reunidas TR
)Aramco site
1- Managing manpower and materials
2- Lead the team in site to achieve our target
3- Coordinate with client the work progress
4- Following the procurement to deliver materials
5- Following the suppliers to deliver the materials
6- Use the available resources to achieve the target
- HARADH PROJECT Aramco site :
1- Temporary facilities (11 GCP sites offices + camp + laydown)
under TR company
2- Loads calculations design for panel board, cables and generators
3- calculations for voltage drop
4- Generators synchronization
5- Fire alarm work in all temporary facilities
6- Electrical quantities surveying
7- Requesting the materials and follow up with vendors the delivery
8- Manage Electrical team in site to complete all related electrical work
9- Coordinate Electromechanical work in site
FADHILI project
- Temporary facilities (sites offices + camp + laydown) under TR company
- Pre engineering Building project
- Materials Submittal and approval
- Engineering work
- Construction site work
- Lighting and power work
- Fire alarm work
- Grounding and lightning work
- PETROFAC PROJECT
- (SUBSTATION, PIB, LAB ,OME) precast buildings under Aramco
- Lighting and power work
- Fire alarm work
- Grounding and lightning work
- Transformers installation
- Power Cable trays installation
- SADARA project :
- Materials Submittal and approval
- Engineering work
- Construction site work
- Lighting and power work
- Fire alarm work
- Grounding and lightning work
- Shop drawings red line modifications and technical quires
- Mcc substation buildings
- Control buildings
- Team buildings
- Operating buildings
- Generator building
3- Mobarak Merai Al-salomi in KSA company (Site Engineer )
- (street lighting) in Alahsa – Alhofof (from 9/8/2011 to 6/10/2012)
- Projects sites(Al-taraf alganoby - Morietba - Al-sieh – Al-Uqair)
- Design street lighting work and
- Quantities surveying
- Following projects with municipalities and electric company
(SCECO).
- Streets lighting (lighting poles - cables – lakes - Electrical
)distribution boards
4- The Egyptian Company for Engineering consulting ( Infra Group)
El-ean Elsokhna (from 9/8/2009 to 1/8/2011)
- Reviewing Electrical Designs relating to site works.
- Executing Electrical works (Buildings – Shops- Health Club –
Treatment Station – Landscape)
- Executing Networks (Low Voltage – Medium Voltage – Low
Current)
- Installation Electrical Units (Boards – Transformers – RMU)
5- Elmotaheda for Contracting &Technology in Hurgada from (1/3/2009 to 1/5/2009)
- Executing Electrical works in Site (Lighting – Power – low current )
- Making Extracts and Quantity Tables.
- Quotations for Electrical units.