Assistant Vice President / Project Director at Power Line Engineering Public Co., Ltd. (2022-01 – Present)
Assistant Vice President / Project Director at Power Line Engineering Public Co., Ltd. (2022-01 – Present)
- Ministry of Interior Building (ศูนย์ราชการกระทรวงมหาดไทยแห่งใหม่), Bangkok - 1,520 Million Baht - Executive management and oversight to successfully complete the project.
- KJL Center, Bangkok - 95 Million Baht - Management and operational direction to complete the project.
- Villa Phuket, Phuket - 35.75 Million Baht - Total project delivery and engineering execution management.
M & E Head Designer & Chief Operating Officer (COO) at Principle Engineering Co., Ltd. (2018-01 – 2022-12)
Core Focus: EIA & Design Submittal Management and Procurement, Business Management.
- Pamookkoo Hotel, Phuket (2019 – 2021) - 180 Million Baht - Design Head and Procurement Manager - Turnkey design & contractor management to complete the project.
- Kata Beach Resort, Phuket (2019 – 2020) - 40 Million Baht - Project Director - Revised drawing management and main contractor oversight.
- Ibis Hotel Karon, Phuket (2018 – 2022) - 230 Rooms - M & E Head Designer - Conceptual Design as per Authority Regulation.
- Stay Hotel, Samui (2021) - 90 Rooms - M & E Head Designer - Revised design drawings and conceptual compliance layout.
Project Director at Power Line Engineering Public Co., Ltd. (2014-01 – 2018-12)
Overall Responsibility: Complete project management, execution, and delivery control.
- Bangkok – Chiangrai Hospital, Chiangrai (2017 – 2018) - 110 Million Baht - Hospital MEP Infrastructure Setup
- Central Phuket Complex, Phuket (2017 – 2018) - 87 Million Baht - Central Department Store, Central Phuket Parking & Tribhum Central Phuket
- Beyond Patong Hotel, Phuket (2016 – 2017) - 155 Million Baht - Hotel 6 Stories (Total area: 9,000 Sq.m.)
- Renovate Central Festival 1, Phuket (2015 – 2016) - 135 Million Baht - Complete renovation of MEP systems for Plaza & Shopping Mall
- Bangkok – Chiangmai Hospital, Chiangmai (2014 – 2015) - 220 Million Baht - Hospital MEP System Management
- Sadao Customs House, Songkhla (2014 – 2015) - 350 Million Baht - Government Border Infrastructure Project
- Cassia Phuket Phase 2 (2016 – 2017) - 79 Million Baht - Luxury Resort & Commercial Hotel Projects
- Boutique Patong Sai 3 (2016 – 2017) - 73.1 Million Baht - Luxury Resort & Commercial Hotel Projects
Project Manager & Site Manager at Power Line Engineering Public Co., Ltd. (2004-01 – 2013-12)
- Amway Head Office, Bangkok (2011 – 2013) - 218 Million Baht - Installation of comprehensive electrical & communication networks.
- Supreme Complex, Bangkok (2010 – 2011) - 250 Million Baht - Electrical & communication system with total transformer capacity of 13 x 2,000 KVA (22 KV system).
- Central Pattaya Beach, Pattaya (2008 – 2009) - 300 Million Baht - Mall & Department Store. Total transformer capacity: 13 x 2,000 KVA (22 KV system).
- Tesco Lotus Hypermarkets, Pranburi & Chiangmai (2008) - 108.5M Baht / 37.5M Baht - Pranburi: 2 x 1,600 KVA (22 KV system) / Chiangmai: 2 x 2,000 KVA (22 KV system)
- Jungceylon Phuket, Phuket (2004 – 2005) - 1,162 Million Baht - Large Plaza Arcade and Hotel. High-capacity transformer setup: 2 x 1,600 KVA and 5 x 2,000 KVA (33 KV system).
- Vichaiyut Hospital, Bangkok (2005 – 2006) - 310.9M Baht - Transformer capacity system: 2 x 1,600 KVA (24 KV system).
Project Engineer & Site Engineer at Power Line Engineering Public Co., Ltd. (1996-01 – 2007-12)
- Dubai Lagoon, Dubai, UAE (2006 – 2007) - 900 Million Baht - Condominium complex. Heavy infrastructure installation: 50 x 1,600 KVA (11 KV system).
- Tesco Lotus / Home Pro Stores, Bangpakok, North Pattaya, Rama II (2001 – 2003) - 115.2M Baht / 115.0M Baht / 35.1M Baht - Bangpakok: 2 x 2,000 KVA (24 KV) / North Pattaya: 2 x 2,000 KVA (22 KV) / Home Pro Rama II: 2 x 1,000 KVA (12 KV)
- Tesco Lotus Nongkai, Nongkai (2003) - 20 Million Baht - 1 x 1,000 KVA, 1 x 1,250 KVA 22 KV system.
- Phuket Arcadia Hotel (Phase 3), Phuket (2000) - 77.5 Million Baht - Transformer capacity installation: 2 x 1,000 KVA (33 KV system).
- Lotus Fortune Town, Bangkok (1999 – 2000) - 48.9 Million Baht - Renovation & Turnkey Design electrical framework.
- CDT-Rayong, Rayong (1997 – 1998) - 420 Million Baht - Industrial plant system setup: 6 x 2,000 KVA & 1 x 1,000 KVA (22 KV system).
- Lotus Supercenters, Ram-Indra, Minburi, South Pattaya (1996 – 2000) - 102.1M Baht / 103.4M Baht / 75.0M Baht - Ram-Indra: 2 x 2,000 KVA (24 KV) / Minburi: 2 x 2,000 KVA (24 KV) / South Pattaya: 2 x 2,000 KVA (22 KV)