Logistics Manager - Ctrl's Data Center - Mahape, New Mumbai
Currently working as a Logistics Manager for DC 8 & 9 Bldg.
- Coordinate the operational slots for the material hoist, mobile crane, and gate entry crane
- Plan daily material shifting activities for all vendors and allocate timing slots to ensure smooth project material movement
- Collect delivery information from vendors 2 days in advance to map out daily time slots based on their assigned floors
- Arrange timing slots on a FIFO (First Informed, First Priority) basis
- Ensure the material hoist operator only shifts materials after the gate entry process is fully completed
- Plan material shifting slots based on information received via email and the DC 8 & 9 Logistics WhatsApp group
- Gather material delivery details 2 days in advance to plan crane availability accordingly
- Strictly instruct all gate security personnel not to allow any delivery vehicle to enter the site without prior permission from the Logistics Manager
- Ensure vendors present a valid challan for returnable materials, which must be signed and stamped by site security upon exit
- Direct security to log all unloaded materials manually in the register, stamp the gate entry for confirmation, and process the paperwork for subsequent Material Inspection Reports (MIR) and billing
- Verify the quality, quantity, and supporting documentation (e.g., challans, invoices, packing lists, test certificates, and gate passes) for all incoming vendor materials
- Conduct site visits for new vendors to explain the site logistics plan and guide them through a physical walkthrough from the ground floor to their respective working floors
- Coordinate with vendor labor and supervisors to guide them on material lifting and shifting procedures, including the arrangement of signalmen and flagmen
- Instruct all teams to secure mandatory safety permits before commencing any lifting and shifting activities
- Ensure lifting belts, wire rope slings, and D-shackles are strictly utilized for loading and unloading
- Guide vendors to shift their material accessories directly to their designated floor warehouses or secure store areas
- Enforce safe material packaging standards to prevent damage during loading and unloading activities
- Monitor gate entries closely to maintain strict control over material inventory on site
- Manage site space effectively for temporary vendor material stacking and smooth vehicle movement
- Plan and design structures to minimize material waste and maximize future component disassembly
- Sort debris at the site into specific streams like concrete, bricks, steel, wood, and plastic
- Crush and wash concrete and masonry into recycled aggregates or sand, and route metals or glass to specialized recycling units
- Transport non-recyclable residues safely to designated facilities
Sr. Logistics / Store Manager - BLUE STAR LIMITED
(2024-12-03 - 2026-03-06)
- Plan site set-up to move labour, plant, and materials around site efficiently (hoarding, gates, site accommodation, cranes, hoists, security, temporary services, material delivery and waste management strategy, catering)
- Plan internal and external logistics routes through the project phases focusing on separation of vehicles, machinery and people
- Lay down areas and offloading points
- Pre-plan the usage of key assets such as hoists to ensure planned assets meet the needs of the program
- Responsible for all traffic management internally and externally, weighbridges and road network cleanliness
- Manage installation of site accommodation and manage these facilities
- Create operational procedures and method statements
- Organise site inductions, ensure induction records are securely stored
Sr. Store In charge - STRONG BUILT CONSTRUCTION PVT.LTD - Mumbai
(2024-06-11 - 2024-11-15)
- Prepare New site set-up to move labour, plant, and materials around site efficiently (hoarding, gates, site accommodation, cranes, hoists, security, temporary services, material delivery and waste management strategy and logistics)
- Plan internal and external logistics routes through the project phases focusing on separation of vehicles, machinery and people
- Lay down areas and offloading points
- Pre-plan the usage of key assets such as hoists to ensure planned assets meet the needs of the program
- Describe the characteristics of the site, including site access/egress, storage capacity and arrangement by programmer, labor, hoists, cranes etc
- Use the description to produce daily, weekly and long term movements plans arrange excess material moving / transferring to other requested purchase order or plan to move on required project or site
- Understand procurement arrangements and site logistics and administrations
- Control materials in and out of site and submits report of material balance, excess, shortage, damage, rejected
Logistics Manager - CAPACITE INFRA PROJECT LIMITED
(2021-08-17 - 2024-04-12)
- Plan site set-up to move labor, plant, and materials around site efficiently (eg hoarding, gates, site accommodation, cranes, hoists, security, temporary services, material delivery and waste management strategy, catering)
- Plan internal and external logistics routes through the project phases focusing on separation of vehicles, machinery and people
- Lay down areas and offloading points
- Pre-plan the usage of key assets such as hoists to ensure planned assets meet the needs of the program
- Responsible for all traffic management internally and externally, weighbridges and road network cleanliness
- Manage installation of site accommodation and manage these facilities
- Create operational procedures and method statements
- Organize site inductions, ensure induction records are securely stored
- Create a schedule of logistics meetings and ensure logistics is represented at site meetings
Store Incharge - STRONG BUILT CONSTRUCTION PVT.LTD - Mumbai
(2018-04-13 - 2019-04-30)
- Track incoming and outgoing building materials (civil, electrical, and mechanical supplies)
- Run Goods Receipt Notes (GRN) and update inventory software
- Conduct routine stock audits to prevent theft, loss, and material damage
- Maintain optimal stock levels to avoid project delays
- Coordinate material drop-offs with suppliers and transport teams
- Check delivered goods for correct quantities and high quality
- Work with purchase departments to plan future material needs
- Organize proper on-site storage and safe stacking of heavy items
- Enforce workplace safety and cleanliness rules in the storage area
- Keep accurate paper and digital records for project audits
- Report daily stock consumption and inventory statuses to project directors
- Manage warehouse equipment maintenance
Site In charge - VIRANI CONSTRUCTION - KAUSA THANE
(2016-01 - 2018-02)
- Monitor daily work progress, assign tasks to laborers, and guide subcontractors
- Enforce safety protocols (like wearing Personal Protective Equipment or PPE), run safety