Project Director – HNTB, Kansas City, USA [Nov 2022 to date]
I’m directing all aspects of project management for the design of the New Des Moines International Airport Terminal with the garage parking building, landside, and airside area of the Project.
Project
- Des Moines International Airport, Des Moines. IA, USA | Estimated project cost: USD 700 Million
Terminal Design Manager – Paslay Group – PG, Kansas City, USA [April 2019 to Nov 2022]
As a client representative, I monitor and deliver the New Kansas City International Airport Terminal with the Project's garage parking building, landside, and airside area.
- Managing ongoing assessment and evaluation of airport, utility, airline stakeholders, and aviation authority requirement implementation, evaluation, and recommendation for proposed substitutions or alternates during construction.
- I monitor contractor multidisciplinary design/BIM compliance with the Basis of Design and construction development activities, assuring expediency & continuity of production to deliver approved budgets & schedules objectives.
Project
- Kansas City International Airport, Kansas City, USA | Estimated project cost: USD 1,5 Billion
Senior Project Design Manager - Italiana Costruzioni Como - ICC JV, Doha, Qatar [June 2016 to March 2019]
As a Head of the Engineering Department, I directed the design engineering documentation and successfully delivered the Al Qassar Metro Stations construction as part of a multi-billion project.
- Managing teams of over 50 internal and consultant personnel throughout multidisciplinary design/BIM and construction activities, assuring expediency & continuity of delivery objectives for approved budgets & schedules.
- Support the management of the program for minimizing the impact of design & construction-related risks & claims, client liaison, handling contract negotiations, project scopes, delivery schedules, budgets, and fees.
Project
- Red Line North and Gold Underground, Doha, Qatar | TC: $ 3.6 Billion | 11 Metro stations with shelters (completed 2019)
Lead Project Manager - Parsons International Ltd, Doha, Qatar [Apr 2013 to June 2016]
I directed all aspects of project management for the design & construction supervision of the assigned contract packages.
- Coordinated pre-construction & periodic review and evaluation of consultant's & contractor's performance. Review contractor’s schedules against the master project documents and monitor performance, assuring completion on time & within budget.
- Facilitate optimum utilization of company resources, assuring achievement of program objectives related to design delivery by managing/participating in in-house technical reviews of shop drawings and specifications of materials.
Project
- Hamad International Airport, Doha, Qatar | TC: $ 16 Billion | New facilities include a passenger terminal with the hotel, Emiri terminal, Qatar Airways First Class Lounge, MOCC & MOI Control Data Center (completed 2016)
Project Manager/Associate - UPG Lamda DBA & Design Group, Abu Dhabi, UAE [Aug 2012 - Mar 2013]
I directed detailed project scope documentation of design, engineering, construction, handover & commercial matters, ensuring project delivery.
- I have identified & mitigated all risks throughout all project phases. In addition, I am implementing a value engineering program to identify and exploit all cost-saving opportunities and improve project margins.
Project
- Kempinski Hotel, Dubai, UAE | 5* hotel in Business Bay | TC: $ 55 million | 20-story business hotel
Project Manager - KEO International Consultants, Abu Dhabi, UAE [Jul 2008 - Jul 2012]
I directed projects and positioned the firm to take advantage of rapid growth and marketplace expansion.
- Reviewed subcontract documents and coordinated with subcontractors for fulfilling contractual obligations in coordination with civil, structural & MEP engineers and landscape architects, assuring completion on time and within approved budgets.
- Led, Supervised, and mentored a 30-member team providing comprehensive technical support to projects, solving queries & evaluating the performance of team members, and prepared Fire & Life Safety Code analysis as per IBC & NFPA.
Projects
- Doha Grand Park, Doha Qatar | TC: $ 700 million | Recreational Park on an area of 2 million m2
- Qasr Al Ain Hotel | 5* Waldorf Astoria in Al Ain UAE | TC: $ 650 million | 4-story building
- Junaibi Tower, Abu Dhabi UAE | Project completed in 2013 | TC: $ 20 million | 12-story tower
- Abu Dhabi Future Schools, Phase 3, Al Ain UAE | Project completed in 2011 | schools for 1250+240 students.
- National Towers, Abu Dhabi UAE | St. Regis Hotel | Project completed in 2013 | TC: $ 435 million | 65 & 52 -story towers.
Emirates Flight Catering Extension, Dubai UAE | Total estimated cost: USD 100 million
- EFKC-1 & EFKC-2. Extension and the total built-up area is 38,769 m2
- EKFC-3. New 3-story facility with docking area and food preparation area. The total built-up area is 28,647 m2
Dar Al-Dhabi Complex, Reem Island, Abu Dhabi UAE | TC: $ 380 million
- Al Sharq West Tower – 35-story residential tower and Al Sharq East Tower – 34-story residential tower
- Al Reem Residential Tower – 7-story multi-family facility and Al Reem Commercial Tower – 7-story office building
Seef Vistas, Seef District Bahrain | Mixed-used development | TC: $ 440 million.
- Tower 1 – 26-story 5* hotel (Shaza) tower with 186 guest rooms & 216 serviced apartments
- Towers 2, 3 & 5 – 24, 28 & 35 stories office buildings and Tower 4 – 34-story residential tower
Senior Project Architect - GREC Architects, Chicago, IL USA [ Dec 2007 - Jun 2008]
I directed the development & delivery of the design and construction documentation.
- Westin Hotel Golf Resort & Spa | 5* Hotel in Abu Dhabi UAE | Project completed in 2011 | TC: $ 100 million
Senior Project Architect - Pappageorge Haymes Ltd, Chicago IL USA [ Nov 2000 - Oct 2007]
I directed the design and construction documentation of assigned high-rise building projects and the conversion of landmark buildings to residential towers.
Projects
- Grant Park One Museum Park West | Project completed in 2009 | TC: $ 165 million | 54-story high-rise
- Grant Park One Museum Park East | Project completed in 2008 | TC: $ 190 million | 62-story high-rise.
- Museum Park Palace Tower | Project completed in 2007 | TC: $ 50 million | 23-story high-rise.
- Museum Park Tower 4 | Project completed in 2006 | TC: $ 80 million | 37-story residential tower
- Museum Park Lofts 2 | Project completed in 2006 | TC: $ 42 million | 21-story residential tower.
- University Commons – Refurbishment/Fit-out | Project completed in 2005 | TC: $ 38 million
- Museum Park Tower 3 | Project completed in 2005 | TC: $ 35 million | 26-story residential tower.
- Museum Park Tower 2 | Project completed in 2003 | TC: $ 40 million | 21-story residential tower.
- The Montgomery Tower – Refurbishment/Fit-out | Project completed in 2003 | 28-story residential tower renovation.
- Museum Park Tower 1 | Project completed in 2002 | TC: $ 25 million | 20-storey residential tower.
Construction Supervisor - U.N. Housing Projects, Derventa, Bosnia & Herzegovina [Sep 1999 - Sep 2000]
I managed Hilfswerk (Austria) & Children’s Relief Association (Germany) construction supervision.
- Reconstruction of war-damaged assets such as 120 houses, a post office building & sports Arena ‘Breza.’
Senior Architect - Servico Technische Betriebsfuhrung und Burodienst, Moscow, Russia [Jun 1998 - Jul 1999]
We have provided architectural services for office areas of the company’s permanent clients, including IBM Russia, Bank Austria Creditanstalt Moscow, Gazprom oil refineries & the Comity of the European Commission.
Internship / Architect - MetriCo, Belgrade, Serbia [Oct 1996 – May 1998]
Prepared architectural & construction documents for interior & exterior designs for various projects.
- Kombank Arena (Belgrade Arena), Serbia. Universal arena for sports and culture events, a capacity of 25,000 seats
- Teakwood (Multiplex Cinema), Belgrade, Serbia.